23.1Numbers that are often confusing
In simple wordsContract questions mostly focus on percentages, days, and limits — here they are all in one place.
Summary Table
| Subject | Correct | Common Mistake |
|---|---|---|
| Bid Security (ACS-11, 13.03.2026) | All works — 2% of Estimated Cost | ₹2 lakh + 0.5% (This is old) |
| Old formula — Maximum | ₹1 crore | ₹50 lakh |
| Labour Cooperative Society | 50% Bid Security | Full exemption |
| Startup (DPIIT — Department for Promotion of Industry and Internal Trade) | Exemption | 50% |
| PG (Performance Guarantee) | 5%, 21 days; 12% p.a. up to 60 days | 10%, 30 days |
| PG Validity | Completion date + 60 days | + 90 days |
| Bid Security BG Validity | Bid validity + 90 days | + 60 days |
| APG (ACS-11) | 5% on bids lower by more than 5% | On bids lower by more than 10% |
| SD (Security Deposit) | 5%; 6% from bills | 10%; 5% per bill |
| SD — in the form of BG (Bank Guarantee) | Contracts of ₹50 crore and above | ₹100 crore |
| LD (Liquidated Damages) | 0.05%–0.30% per week, maximum 5% | 0.5% per week, maximum 10% (This is for Stores) |
| Commencement of work | Within 15 days of LOA (Letter of Acceptance) | 30 days |
| Force Majeure | Notice 30 days; Termination if hindrance exceeds 120 days | 90 days |
| Termination Notice | 7 days + 48 hours | 15 days + 7 days |
| Sub-letting (ACS-11) | Maximum 40%; Self ≥60% | 50% |
| Bid Capacity limit | Above ₹10 crore (ACS-11; previously ₹20 crore) | ₹50 crore |
| Bid Capacity Formula | (A×N×2) − 0.33×N×B | (A×N×2.5) − B |
| Financial Eligibility | V/N or V, whichever is less (ACS-1, 14.07.2022) | 1.5 V/N (Old) |
| Technical Eligibility | 7 years; 3×30% / 2×40% / 1×60% | 5 years; 35% |
| No Eligibility Criteria | Up to ₹50 lakh | Up to ₹1 crore |
| Notice Period | 21 days; e-Tender up to ₹2 crore 14 days (Associate Finance) | 30 days |
| SLT (Special Limited Tender) | Not less than 4, better more than 6; ≥14 days | 3 to 5 |
| Direct Acceptance | Up to ₹50 lakh, SG/JAG/SS(IC) | ₹1 crore |
| 2-member TC (Tender Committee — e-tender) | ₹50 lakh–₹5 crore | Up to ₹2 crore (This is of 2017) |
| e-RA (Works) | Above ₹50 crore, Optional (21.11.2024) | Mandatory |
| PVC (Price Variation Clause) | ₹2 crore (Contract Agreement Value); Fixed 15% | Tender Value; 10% |
| Conciliation | Advertised Value ≤ ₹50 crore | ≤ ₹100 crore |
| Sole Arbitrator (GCC 2022 Original) | Claims up to ₹1 crore | ₹25 lakh (This is of old GCC) |
| Demand for Arbitration | After 120 days, within 180 days | 90–120 days |
| Final Claims | Within 90 days of intimation that Final Bill is ready | 180 days |
| ACS-12 Arbitrator Age | Less than 70 years | 65 |
| Integrity Violation — Banning | At least 1 year | Maximum 1 year |
| Service PG | 5% (24.05.2024) | 10% |