Role of Accounts (Associate Finance) in the Contracting Process

Contracts & Tenders • Part 22 / 24 • Appendix-III A IREM Examination

हिंदी में पढ़ें

In this part

  1. Step-by-Step Role
  2. Finance Member — Checklist in TC
  3. Pre-check of On-account Bill (Key Points)
  4. Common Audit Objections
  5. Golden Rules

First sub-topic (sample)

22.1Step-by-Step Role

In simple words

The role of Accounts/Finance at every stage from Tender to final payment.

Summary Table

Stage What Accounts/Finance Does
Estimate/Sanction Vetting of Estimate, Allocation, availability of funds — No tender without a Sanctioned Estimate
Tendering Method Limited/Special Limited/Single Tender, reduction in notice period (14 days up to ₹2 crore) — Finance Concurrence/Consultation
Tender Document Eligibility Criteria, Bid Security, Special Conditions — compliance with rules (Vetting in large/special cases)
Tender Committee Member (Finance) — Eligibility, rate-reasonableness, financial implications, rule-compliance; Dissent Note
Direct Acceptance (up to ₹50 lakh) Pre-vetting of LOA (Letter of Acceptance) (Item, rate, quantity)
Agreement Vetting of Agreement/Supplementary Agreement (as per MSOP)
PG/SD/BG Register; Bank confirmation of BG (Bank Guarantee); monitoring of validity; timely extension/encashment
On-account Bill Pre-check — Measurement, rate, contract conditions; deductions (SD 6%, TDS, GST-TDS, Cess, recovery of advances)
Advances Provision in contract, BG, interest-calculation, recovery-schedule
Variations Vetting of Variation Statement and vitiation statement; rate-analysis of new NS items
Extension of Time Correct classification of 17A/17B; rate/calculation of LD (Liquidated Damages); applicability of PVC (Price Variation Clause)
PVC Bill Indices, weights, base month, rules for extended period
Final Bill Reconciliation of all recoveries; No-Claim; Final Supplementary Agreement
SD (Security Deposit) Return Maintenance certificate, final payment, no pending claim/Lien
Disputes Railway's side in Arbitration — financial scrutiny of claims; provision for Award payment; time-limit for Section 34 challenge
Full preparation in the app

All parts in Hindi + English, subject-wise MCQs and mock tests — create a free account.

Start free
‹ Previous: Service Contracts, EPC, Consultancy and Other Special ContractsAll parts — Contracts & TendersNext: Exam Traps — At a Glance ›
All exams & subjects (Hindi) • Login • शिक्षक भर्ती (RPSC / REET) नोट्स • Telegram channel • गोपनीयता नीति • नियम व शर्तें • संपर्क