21.1GCC for Services, 2018
In simple wordsSeparate general conditions for service contracts (cleaning, housekeeping, etc.).
Summary Table
| Point | Description |
|---|---|
| Issued | January 2018 (Declared by Indian Railways on 05.02.2018) — by the Transformation Cell of the Railway Board; separate GCC (General Conditions of Contract) for services for the first time |
| Background | Committee of Executive Directors — for simplification and quality improvement of service contracts; while creating the Standard Bidding Document (SBD) for housekeeping, the need was felt that it is difficult to run services using the "Works" GCC |
| Applicable to | Services in non-operational areas — housekeeping, facility management, cleaning, etc. |
| New Concepts | (1) Digital Labor Management System (attendance/payment of workers); (2) Stepped Performance Guarantee instead of SD (Security Deposit); (3) Access to liquidity — as an Eligibility Criteria; (4) Disqualification on violation of certain specific provisions |
| Objective | Outcome-focused, simple contract; emphasis on service-level |
Performance Guarantee in Service Contract
- Original provision (Para 4.11) — 10% of the Contract Value, 2.5% each in four separate parts, within 30 days from LOA (Letter of Acceptance).
- Railway Board Letter 2017/EnHM/25/11 dated 24.05.2024 — In reference to the Ministry of Finance OM dated 01.01.2024 (Amendment in Rule 171 of GFR 2017 — Performance Security), PG in all future service contracts reduced from 10% to 5% (Board — M/TRS and MF).
- Benefit of stepped PG — Reduced financial burden on the contractor, but pressure on service quality due to forfeiture of a portion of PG upon service deficiency.
Service Contract — Eligibility (In brief)
- Technical — Similar service contract in previous years (e.g., a single similar contract of 35% of the advertised value); ongoing contracts also valid if bill payments of that value have been made.
- Financial — Total financial turnover (e.g., 1.5 times of the advertised bid value in previous years).
- Bid Capacity — Remaining capacity after commitments of other contracts.
Service Contract — Acceptance Powers
- Board letter 2023/F(X)II/PW/1 dated 27.12.2023 — Separate table for Division-controlled units and HQ/other units.
Labor Law Compliance (Both Service and Works)
- Compliance with Contract Labour (Regulation and Abolition) Act, 1970, Minimum Wages, EPF (Employees' Provident Fund), ESI (Employees' State Insurance); responsibility of the Principal Employer (Railways) in case of non-payment by the contractor — therefore, Railways verifies and, if necessary, recovers from the contractor's bills to pay the workers.
- Building and Other Construction Workers (BOCW) Cess — Deduction from bills of construction works.