In simple wordsContract questions in the bank rest on four things — (1) type of tender and notice period, (2) rate and timing of EMD/PG/SD, (3) rates on quantity variation, (4) who accepts. In several places two bank keys differ — both are given.
1Forms and types of contract
- Engineering Code — 3 groups of works/supplies, 3 forms of contract (lump sum, piece-work, schedule), 3 kinds of tender; zonal contract = piece-work.
- Zonal contract — permissible excess 25%; each work order — Rs 5 lakh (works-accounts and chapter-4 keys) or Rs 10 lakh, period 1 July–30 June (chapter-8 key).
- Rate contract — supply on demand of any quantity at fixed rates within a period; development orders — for indigenous new technology.
- "Time is the essence of contract" — a specific GCC clause; an agreement enforceable by law = contract; integral documents — GCC, SCC, specifications, rates and quantities; two witnesses on execution.