Dispute Resolution — Excepted Matters, Conciliation, DAB and Arbitration (Para 63, 64)

Contracts & Tenders • Part 19 / 24 • Appendix-III A IREM Examination

हिंदी में पढ़ें

In this part

  1. Three-tier System (GCC 2022)
  2. Excepted Matters
  3. Conciliation (Para 63) — Details
  4. DAB (Para 63.2)
  5. Demand for Arbitration — Time-limits (Para 64(1))
  6. Arbitral Tribunal — Basic framework of GCC 2022 (Before ACS-12)
  7. Supreme Court — CORE vs. ECI-SPIC-SMO-MCML (JV), Constitution Bench, 08.11.2024
  8. ACS-12 (12.08.2026) — New framework of Arbitration (Para 64(3))
  9. Arbitration and Conciliation Act, 1996 — Useful Sections

First sub-topic (sample)

19.1Three-tier System (GCC 2022)

In simple words

Three levels of dispute resolution — Conciliation → DAB (Dispute Adjudication Board) → Arbitration.

Summary Table

Level When Feature
Conciliation — Para 63 Advertised value of tender up to (including) ₹50 crore Sole Conciliator; settlement by mutual consent
Dispute Adjudication Board (DAB) — Para 63.2 Advertised value more than ₹50 crore Members — Retired senior officers etc.; Decision
Arbitration — Para 64 If not resolved by Conciliation/DAB Under Arbitration and Conciliation Act, 1996
In detail

Dispute resolution in GCC 2022 is a ladder — first an attempt at consensual solution, and only if it fails, then Arbitration.

  • First Level — According to contract size — Conciliation (Para 63): In contracts with advertised value up to ₹50 crore — a conciliator attempts to bring both parties to a consensual agreement. Dispute Adjudication Board — DAB (Para 63.2): In contracts above ₹50 crore — a board consisting of members like retired senior officers, which gives a decision. DAB is used in large contracts because disputes there are complex and require immediate decisions.
  • Second Level — Arbitration (Para 64) — If not resolved by Conciliation or DAB — under the Arbitration and Conciliation Act, 1996.

The objective of this sequence is that most disputes get resolved in a cheap and fast manner at the first stage itself.

  • Similar framework in EPC (Engineering, Procurement and Construction) contracts — Clause 24.1 (Conciliation), 24.2 (DAB), 24.3 (Statutory Arbitration Tribunal – SAT); In EPC, DAB must be constituted within 90 days of the agreement.
Full preparation in the app

All parts in Hindi + English, subject-wise MCQs and mock tests — create a free account.