18.1Two Types
In simple wordsA contract ends in two ways — at the convenience of the Railway, or due to the contractor's default.
Summary Table
| Para | Type | Reason |
|---|---|---|
| 61 | Termination for convenience | Paucity of funds, requirement of work ends, policy change or any other reason — no default of the contractor |
| 62 | Termination due to contractor's default | Failure/default of the contractor |
In detail
Termination of contract is of two types, and the consequences of both are completely different — because in one, it is no one's fault, and in the other, it is the contractor's fault.
- Para 61 — Termination for Railway's convenience — Paucity of funds, end of requirement for the work, policy change or any other reason — no default of the contractor. Therefore, the contractor receives payment for the work done and materials at site. This decision is an Excepted Matter — meaning it cannot be challenged in arbitration; the Railway's decision is final.
- Para 62 — Termination due to contractor's default — Failure or default of the contractor (slow work, poor quality, not following instructions). In this, first a 7 days' notice (opportunity to rectify the default) is given, then a 48 hours' final notice, and if there is still no improvement, termination follows — termination without completing the notice period can be held illegal. After termination, SD is forfeited and PG is encashed, and the remaining work is carried out through a new tender, in which that contractor cannot participate.