17.1Sequence — For Memory
In simple wordsSequence after completion of work — Completion Certificate (Release of PG) → Maintenance Period → Final Bill → Release of SD (Security Deposit).
Physical completion → Completion certificate (48) → return of PG
↓
Maintenance period (47) → Maintenance certificate (50)
↓
Final measurement → Final bill (51) + No-claim / Final Supplementary Agreement
↓
Return of SD (16(2)) → Railway's liability ends (50(2))
Example — Final stage of a building work:
- 30 June — Building completed, debris removed, deficiencies rectified → Completion Certificate → PG (5%) returned.
- Maintenance Period (assume 6 months) until 31 December — Meanwhile, a leak was found in the roof; contractor repaired it.
- January — Maintenance Certificate; Final Measurement → Final Bill, contractor's No-Claim/Final Supplementary Agreement.
- Thereafter — SD (5%) returned; now no liability of Railway remains.
- If the leak was not repaired → Railway would have done it itself/through another agency and deducted the cost from SD.