16.1Measurement and Running Payment (GCC Part II, Para 44–46)

In simple words

Payment from running bills based on the measurement of work.

Summary Table

Para Provision
44 Quantities in the Bill of Quantities are estimated — Payment on actual measured quantity
45 Measurement by Railway — In the presence of contractor/representative; in Measurement Book (MB); signature of contractor; Railway's measurement valid in case of absence
46(1) On-account Bill — Monthly or at prescribed intervals, based on measurement of work done
46(3) "On-account payments do not prejudice the final settlement" — These are only advances; adjustment in the Final Bill
46(5) Mode of Payment — Electronic (ECS/NEFT/RTGS)
In detail

The basic principle of payment to the contractor is: Payment will be for work actually performed and measured.

  • Estimated vs Actual (44) — Quantities in the Bill of Quantities are only estimated; payment is based on the actually measured quantity.
  • Measurement (45) — Done by the Railway, in the presence of the contractor or their representative, in the Measurement Book, with the contractor's signature; however, if the contractor does not attend, the Railway's measurement alone is valid — so that the contractor cannot stall payment by withholding measurement.
  • On-account Bill (46(1)) — Monthly or at prescribed intervals, based on the measurement of work performed.
  • On-account Payment is not Final (46(3)) — On-account payments are only advances; everything is adjusted in the final bill — meaning if payment is made in any running bill, it does not imply that the Railway has finally accepted that work.
  • Mode (46(5)) — Electronic (ECS/NEFT/RTGS).
  • IR-WCMS (Works Contract Management System) — Online measurement, e-MB, bill processing, payment tracking.
  • Deductions from running bills — SD (6%), Income Tax TDS (Tax Deducted at Source), GST (Goods and Services Tax) TDS, Labour Cess (BOCW cess), recovery of advances (Principal + Interest), cost of electricity/water/materials, LD (Liquidated Damages).
  • Post-Payment Audit (Para 51(2)) — The Railway reserves the right to recover overpayments by conducting audit/technical checks even after payment.
Full preparation in the app

All parts in Hindi + English, subject-wise MCQs and mock tests — create a free account.

Start free
‹ Previous: Variations — GCC Part II, Para 42All parts — Contracts & TendersNext: Completion, Maintenance, Final Bill and No-Claim ›
All exams & subjects (Hindi) • Login • शिक्षक भर्ती (RPSC / REET) नोट्स • Telegram channel • गोपनीयता नीति • नियम व शर्तें • संपर्क