16.1Measurement and Running Payment (GCC Part II, Para 44–46)
In simple wordsPayment from running bills based on the measurement of work.
Summary Table
| Para | Provision |
|---|---|
| 44 | Quantities in the Bill of Quantities are estimated — Payment on actual measured quantity |
| 45 | Measurement by Railway — In the presence of contractor/representative; in Measurement Book (MB); signature of contractor; Railway's measurement valid in case of absence |
| 46(1) | On-account Bill — Monthly or at prescribed intervals, based on measurement of work done |
| 46(3) | "On-account payments do not prejudice the final settlement" — These are only advances; adjustment in the Final Bill |
| 46(5) | Mode of Payment — Electronic (ECS/NEFT/RTGS) |
In detail
The basic principle of payment to the contractor is: Payment will be for work actually performed and measured.
- Estimated vs Actual (44) — Quantities in the Bill of Quantities are only estimated; payment is based on the actually measured quantity.
- Measurement (45) — Done by the Railway, in the presence of the contractor or their representative, in the Measurement Book, with the contractor's signature; however, if the contractor does not attend, the Railway's measurement alone is valid — so that the contractor cannot stall payment by withholding measurement.
- On-account Bill (46(1)) — Monthly or at prescribed intervals, based on the measurement of work performed.
- On-account Payment is not Final (46(3)) — On-account payments are only advances; everything is adjusted in the final bill — meaning if payment is made in any running bill, it does not imply that the Railway has finally accepted that work.
- Mode (46(5)) — Electronic (ECS/NEFT/RTGS).
- IR-WCMS (Works Contract Management System) — Online measurement, e-MB, bill processing, payment tracking.
- Deductions from running bills — SD (6%), Income Tax TDS (Tax Deducted at Source), GST (Goods and Services Tax) TDS, Labour Cess (BOCW cess), recovery of advances (Principal + Interest), cost of electricity/water/materials, LD (Liquidated Damages).
- Post-Payment Audit (Para 51(2)) — The Railway reserves the right to recover overpayments by conducting audit/technical checks even after payment.