13.1Basic Rule
In simple wordsThe contractor cannot give work to anyone else without permission.
- The contractor cannot assign or sublet the contract or any part of it to any other person without the prior written permission of the Railway.
- Sub-letting without permission — Ground for termination of contract (Para 62).
- Even after permission, all obligations and liabilities of the contract remain with the main contractor — the sub-contractor has no direct contractual relation with the Railway.
- Payment only to the main contractor; responsibility for payment to the sub-contractor lies with the contractor.