14.1Commencement of Work and Programme
In simple wordsAfter the LOA (Letter of Acceptance), the work should start on time and according to the programme.
Summary Table
| Point | Provision (GCC Part II) |
|---|---|
| Commencement of Work | Start work within 15 days of receiving the LOA (order) (Para 19(2)) |
| Approved Programme of Work | Contractor shall submit work programme (bar chart/network); same to be the standard after engineer's approval (Para 19(3)) |
| Setting out of Works | Para 19(4) — setting out; contractor's responsibility |
| Engineer's Instructions | Compliance mandatory (Para 20(1)); modifications only if authorized (20(2)); extra work (20(3)) |
| Time | Time is of the essence of the contract (Para 17B) |
In detail
These provisions of GCC Part II are for starting the work on time and as per plan.
- Commencement of work — Within 15 days of receiving the LOA.
- Programme of work — Contractor to give programme in the form of bar chart or network; after approval by the engineer, it is the standard — progress will be measured against it.
- Setting out of works — Correct setting out of work on the ground is the contractor's responsibility — cost of correction in case of error is theirs.
- Engineer's instructions — Compliance mandatory; modifications only authorized; extra work on instruction.
- Time is the essence of the contract (17B) — The legal meaning of "time is the essence" is that delay is a serious breach of the contract — Liquidated Damages (LD) and rights of contract termination rest upon this.