12.1Amount and Recovery
In simple wordsSD = 5% of the contract value as security — either deposited upfront in a lumpsum, or deducted at 6% from each on-account bill; guarantee for work quality and maintenance.
Summary Table
| Point | Provision |
|---|---|
| Amount | 5% of Contract Value (not tender value) |
| Recovery — Option 1 | Entire amount deposited in cash/TDR, etc., before the first on-account bill |
| Recovery — Option 2 | Deduction of 6% from each on-account bill until the full SD (5%) is recovered |
| Bid Security | Bid security of the successful bidder is retained as part of SD; if the full SD is deposited separately (TDR/BG), the bid security can be refunded |
| Contracts of ₹50 Crore and above | SD in the form of Bank Guarantee from a Scheduled Bank — after signing of agreement and before the first on-account payment |
| Interest | No interest on SD (Para 16(3)) |
Security Deposit (SD) is a guarantee of the contractor's good work — it is returned only after the completion of work and maintenance period, so that any defects arising later can be rectified.
- Amount — 5% of the Contract Value (not of the tender value — i.e., the final accepted amount).
- How to deposit — Two options: (1) Entire amount in cash/TDR, etc., before the first on-account bill; or (2) Deduction of 6% from each on-account bill until the full 5% is recovered.
- Bid Security — Bid security of the successful bidder is kept as part of SD.
- Large contracts (₹50 Crore+) — SD in the form of Bank Guarantee, after signing of agreement and before the first on-account payment.
- Interest — No interest on SD.
Example — Contract value ₹2 crore → SD ₹10 lakh; in Option 2, 6% will be deducted from each bill until a total of ₹10 lakh is reached.
- Why 6%? — So that the 5% amount is recovered by the time about 83% (5 ÷ 6) of the work is billed and full security is available before the final stage.
Example — Contract value ₹10 crore → SD = ₹50 lakh. Bid security of ₹20 lakh already available → balance ₹30 lakh. 6% deduction from each on-account bill — ₹6 lakh from a bill of ₹1 crore; balance ₹30 lakh completed when bills reach approximately ₹5 crore.