Security Deposit (SD) — GCC Part II, Para 16(1)–(3)

Contracts & Tenders • Part 12 / 24 • Appendix-III A IREM Examination

हिंदी में पढ़ें

In this part

  1. Amount and Recovery
  2. Refund of SD — Para 16(2)
  3. Forfeiture of SD
  4. In Service Contracts (GCC for Services 2018)
  5. From Accounting Perspective
  6. Bid Security – PG – SD: At a Glance

First sub-topic (sample)

12.1Amount and Recovery

In simple words

SD = 5% of the contract value as security — either deposited upfront in a lumpsum, or deducted at 6% from each on-account bill; guarantee for work quality and maintenance.

Summary Table

Point Provision
Amount 5% of Contract Value (not tender value)
Recovery — Option 1 Entire amount deposited in cash/TDR, etc., before the first on-account bill
Recovery — Option 2 Deduction of 6% from each on-account bill until the full SD (5%) is recovered
Bid Security Bid security of the successful bidder is retained as part of SD; if the full SD is deposited separately (TDR/BG), the bid security can be refunded
Contracts of ₹50 Crore and above SD in the form of Bank Guarantee from a Scheduled Bank — after signing of agreement and before the first on-account payment
Interest No interest on SD (Para 16(3))
In detail

Security Deposit (SD) is a guarantee of the contractor's good work — it is returned only after the completion of work and maintenance period, so that any defects arising later can be rectified.

  • Amount — 5% of the Contract Value (not of the tender value — i.e., the final accepted amount).
  • How to deposit — Two options: (1) Entire amount in cash/TDR, etc., before the first on-account bill; or (2) Deduction of 6% from each on-account bill until the full 5% is recovered.
  • Bid Security — Bid security of the successful bidder is kept as part of SD.
  • Large contracts (₹50 Crore+) — SD in the form of Bank Guarantee, after signing of agreement and before the first on-account payment.
  • Interest — No interest on SD.

Example — Contract value ₹2 crore → SD ₹10 lakh; in Option 2, 6% will be deducted from each bill until a total of ₹10 lakh is reached.

  • Why 6%? — So that the 5% amount is recovered by the time about 83% (5 ÷ 6) of the work is billed and full security is available before the final stage.

Example — Contract value ₹10 crore → SD = ₹50 lakh. Bid security of ₹20 lakh already available → balance ₹30 lakh. 6% deduction from each on-account bill — ₹6 lakh from a bill of ₹1 crore; balance ₹30 lakh completed when bills reach approximately ₹5 crore.

Full preparation in the app

All parts in Hindi + English, subject-wise MCQs and mock tests — create a free account.

Start free
‹ Previous: Letter of Acceptance (LOA), Agreement, Performance Guarantee (PG) and Additional PGAll parts — Contracts & TendersNext: Assignment, Sub-letting and Joint Venture — GCC Part II, Para 7 ›
All exams & subjects (Hindi) • Login • शिक्षक भर्ती (RPSC / REET) नोट्स • Telegram channel • गोपनीयता नीति • नियम व शर्तें • संपर्क