Legal Basis of Contracts — the Contract Act, Article 299, GFR and the Codes

Contracts & Tenders • Part 1 / 24 • Appendix-III A IREM Examination full part free

हिंदी में पढ़ें

In this part

  1. Framework of Rules (Which Rule Where)
  2. Indian Contract Act, 1872 — Sections Useful for the Exam
  3. Article 299 of the Constitution
  4. Finance Code Chapter VI — General Principles of Contracts
  5. Engineering Code Chapter XII — Key Paras
  6. GFR 2017 — Principles (Effect on the Railways)

1.1Framework of Rules (Which Rule Where)

In simple words

Railway contracts are governed by several rules — the Contract Act (the law), Article 299 of the Constitution (contracts in the name of the Government), the Finance/Engineering Codes, the GFR (General Financial Rules) and the GCC (general conditions).

Summary table

Source What it governs
Indian Contract Act, 1872 The basic validity of every contract — proposal, acceptance, consideration, competence, compensation
Article 299 of the Constitution The form and execution of contracts on behalf of the Government (Union/State)
General Financial Rules (GFR) 2017 General principles for procurement and works by the Central Government — transparency, competition, Code of Integrity
Finance Code Vol. I, Chapter VI "Contracts — general principles" (applies to contracts of all departments)
Engineering Code, Chapter XII (para 1201 onwards) Tenders and contracts for works — tender system, notice period, single tender (1214-A), tender notice (1238)
Stores Code Stores/supply contracts (not the subject of this chapter)
GCC April 2022 (Indian Railways Standard General Conditions of Contract) Standard conditions for railway works contracts; amended by Advance Correction Slips (ACS) — up to ACS-11 (13.03.2026) and ACS-12 (12.08.2026)
GCC for Services, 2018 Service contracts (housekeeping, facility management, etc.)
Standard EPC (Engineering, Procurement and Construction) document EPC (design to construction) contracts — with their own dispute-resolution arrangement
Special Conditions Separate conditions of an individual tender — in case of conflict with the GCC, the special conditions normally prevail
Railway Board's letters, CVC (Central Vigilance Commission) guidelines, MSOP (Model Schedule of Powers) Tender Committee, accepting powers, negotiation, e-reverse auction, etc.
In detail

Railway contracts are governed by a layered set of rules. At the base is the Indian Contract Act, 1872, which decides whether any contract is valid. Article 299 of the Constitution prescribes the form in which government contracts must be made and executed. The GFR 2017 sets general principles of transparency, competition and integrity for central procurement and works.

Finance Code Volume I, Chapter VI gives general contract principles for all departments, and Engineering Code Chapter XII deals with works tenders and contracts. The GCC of April 2022, amended up to ACS-12 (12.08.2026), is the standard contract for railway works, while the GCC for Services, 2018 covers service contracts and a standard EPC document covers design-to-construction contracts. Special conditions of an individual tender normally prevail over the GCC where they conflict, and Board letters, CVC guidelines and the MSOP govern tender committees, powers and negotiation.

  • GCC April 2022 was issued by Board's letter 2022/CE-I/CT/GCC-2022/Policy dated 27.04.2022, effective prospectively, with the concurrence of the Finance Directorate. Before it, there was the GCC of July 2020.
  • The GCC has two parts — Part I: Regulations for Tenders and Contracts (registration, bid security, eligibility, two-packet system, etc.) and Part II: Standard General Conditions (SD, PG, extension of time, variations, payments, termination, disputes, etc.).
  • Every ACS takes effect prospectively — i.e. contracts already running continue on the old conditions.

1.2Indian Contract Act, 1872 — Sections Useful for the Exam

In simple words

What a contract is, when it is valid, when it is broken — the basic law is the Contract Act of 1872.

Summary table

Section Provision
2(a) Proposal/offer — signifying willingness to do or abstain from doing something, with a view to obtaining the other's assent
2(b) Acceptance — assent to the proposal; an accepted proposal becomes a "promise"
2(d) Consideration
2(e) Agreement — every promise and every set of promises forming the consideration for each other
2(h) Contract — an agreement enforceable by law
4 When communication is complete — acceptance is complete as against the proposer when it is put in a course of Transmission
5 Revocation of a proposal — can be made before the communication of acceptance is complete
7 Acceptance must be absolute and unqualified — a conditional "acceptance" is actually a counter offer
10 Elements of a valid contract — free consent, competent parties, lawful consideration and object, and the agreement not expressly declared void
11 Competent parties — of the age of majority, of sound mind, not disqualified by law
14–18 Free consent — free from coercion (15), undue influence (16), fraud (17), misrepresentation (18)
23 The object/consideration must be lawful
56 Impossible act — the doctrine of frustration
73 Compensation for breach of contract (loss arising naturally)
74 Sum named in the contract (liquidated damages/penalty) — the aggrieved party gets reasonable compensation, not exceeding the named sum

Applying the Act to the tender process

Example — looking at a tender through the Contract Act:

  1. 1 March — the Railways publish an NIT on IREPS (Indian Railways E-Procurement System) → this is an invitation to offer; it does not bind the Railways to award the work to anyone.
  2. 31 March — contractor A bids ₹4.80 crore, validity 90 days, with bid security → the bid = an offer.
  3. 15 April — A wants to withdraw the bid → under Section 5 the offer can be withdrawn, but the separate agreement not to withdraw within the validity period is broken → bid security forfeited.
  4. (If A had stayed on) 20 May — the Railways send an unconditional LOA → acceptance; the contract is complete.
  5. (Alternatively) the Railways said "do it for ₹4.70 crore" → this is a counter offer; a contract comes into being only if A agrees.

Section 56 — Frustration, example: A contract was made to repair an old station building, but before the work began the building was completely destroyed in a fire → the very subject of the contract no longer exists → the contract becomes void (no party at fault). A work merely becoming costlier or harder is not frustration.

1.3Article 299 of the Constitution

In simple words

Government contracts are valid only if made in the name of the President, in writing, by an authorised officer.

  1. All contracts made in the exercise of the executive power of the Union (or a State) shall be expressed to be made by the President (or the Governor).
  2. Such contracts shall be executed on behalf of the President/Governor by such persons and in such manner as he may direct/authorise.
  3. Neither the President/Governor is personally liable, nor is the person making the contract on their behalf personally liable.

1.4Finance Code Chapter VI — General Principles of Contracts

In simple words

The Finance Code says what must be kept in mind in every contract — clear terms, competition, financial safeguards.

1.5Engineering Code Chapter XII — Key Paras

In simple words

Chapter XII of the Engineering Code — the detailed rules for works contracts.

Summary table

Para Subject
1210 Tender system — the primary duty of the executive is to obtain the best value for the money spent; the tender system should be adopted as far as possible
1211–1214 Circumstances for exceptions to the Open Tender (limited/single/dispensing with tenders)
1214-A Circumstances for a Single Tender
1238 Tender notice period (amended from 24.10.2018)
1239 Scrutiny/publication of the tender notice

1.6GFR 2017 — Principles (Effect on the Railways)

In simple words

The GFR does not apply directly to the Railways, but the Railways also adopt its principles (transparency, competition, fairness).

Exam trap
  • NIT = invitation to offer; tender = offer; LOA = acceptance. Conditional acceptance = counter offer (Section 7).
  • Contract = an agreement enforceable by law — Section 2(h); elements of a valid contract — Section 10.
  • Liquidated Damages — Section 74; compensation for breach — Section 73; frustration — Section 56.
  • Article 299 — contract in the name of the President; the President is not personally liable; the conditions are mandatory.
  • GCC April 2022 — letter 27.04.2022; every ACS is prospective. Latest — ACS-11 (13.03.2026), ACS-12 (12.08.2026).
  • Engineering Code — tender system 1210, Single Tender 1214-A, tender notice 1238.
Full preparation in the app

All parts in Hindi + English, subject-wise MCQs and mock tests — create a free account.

Start free
All parts — Contracts & TendersNext: Types of Contracts ›
All exams & subjects (Hindi) • Login • शिक्षक भर्ती (RPSC / REET) नोट्स • Telegram channel • गोपनीयता नीति • नियम व शर्तें • संपर्क