1.1Framework of Rules (Which Rule Where)
In simple wordsRailway contracts are governed by several rules — the Contract Act (the law), Article 299 of the Constitution (contracts in the name of the Government), the Finance/Engineering Codes, the GFR (General Financial Rules) and the GCC (general conditions).
Summary table
| Source | What it governs |
|---|---|
| Indian Contract Act, 1872 | The basic validity of every contract — proposal, acceptance, consideration, competence, compensation |
| Article 299 of the Constitution | The form and execution of contracts on behalf of the Government (Union/State) |
| General Financial Rules (GFR) 2017 | General principles for procurement and works by the Central Government — transparency, competition, Code of Integrity |
| Finance Code Vol. I, Chapter VI | "Contracts — general principles" (applies to contracts of all departments) |
| Engineering Code, Chapter XII (para 1201 onwards) | Tenders and contracts for works — tender system, notice period, single tender (1214-A), tender notice (1238) |
| Stores Code | Stores/supply contracts (not the subject of this chapter) |
| GCC April 2022 (Indian Railways Standard General Conditions of Contract) | Standard conditions for railway works contracts; amended by Advance Correction Slips (ACS) — up to ACS-11 (13.03.2026) and ACS-12 (12.08.2026) |
| GCC for Services, 2018 | Service contracts (housekeeping, facility management, etc.) |
| Standard EPC (Engineering, Procurement and Construction) document | EPC (design to construction) contracts — with their own dispute-resolution arrangement |
| Special Conditions | Separate conditions of an individual tender — in case of conflict with the GCC, the special conditions normally prevail |
| Railway Board's letters, CVC (Central Vigilance Commission) guidelines, MSOP (Model Schedule of Powers) | Tender Committee, accepting powers, negotiation, e-reverse auction, etc. |
Railway contracts are governed by a layered set of rules. At the base is the Indian Contract Act, 1872, which decides whether any contract is valid. Article 299 of the Constitution prescribes the form in which government contracts must be made and executed. The GFR 2017 sets general principles of transparency, competition and integrity for central procurement and works.
Finance Code Volume I, Chapter VI gives general contract principles for all departments, and Engineering Code Chapter XII deals with works tenders and contracts. The GCC of April 2022, amended up to ACS-12 (12.08.2026), is the standard contract for railway works, while the GCC for Services, 2018 covers service contracts and a standard EPC document covers design-to-construction contracts. Special conditions of an individual tender normally prevail over the GCC where they conflict, and Board letters, CVC guidelines and the MSOP govern tender committees, powers and negotiation.
- GCC April 2022 was issued by Board's letter 2022/CE-I/CT/GCC-2022/Policy dated 27.04.2022, effective prospectively, with the concurrence of the Finance Directorate. Before it, there was the GCC of July 2020.
- The GCC has two parts — Part I: Regulations for Tenders and Contracts (registration, bid security, eligibility, two-packet system, etc.) and Part II: Standard General Conditions (SD, PG, extension of time, variations, payments, termination, disputes, etc.).
- Every ACS takes effect prospectively — i.e. contracts already running continue on the old conditions.
1.2Indian Contract Act, 1872 — Sections Useful for the Exam
In simple wordsWhat a contract is, when it is valid, when it is broken — the basic law is the Contract Act of 1872.
Summary table
| Section | Provision |
|---|---|
| 2(a) | Proposal/offer — signifying willingness to do or abstain from doing something, with a view to obtaining the other's assent |
| 2(b) | Acceptance — assent to the proposal; an accepted proposal becomes a "promise" |
| 2(d) | Consideration |
| 2(e) | Agreement — every promise and every set of promises forming the consideration for each other |
| 2(h) | Contract — an agreement enforceable by law |
| 4 | When communication is complete — acceptance is complete as against the proposer when it is put in a course of Transmission |
| 5 | Revocation of a proposal — can be made before the communication of acceptance is complete |
| 7 | Acceptance must be absolute and unqualified — a conditional "acceptance" is actually a counter offer |
| 10 | Elements of a valid contract — free consent, competent parties, lawful consideration and object, and the agreement not expressly declared void |
| 11 | Competent parties — of the age of majority, of sound mind, not disqualified by law |
| 14–18 | Free consent — free from coercion (15), undue influence (16), fraud (17), misrepresentation (18) |
| 23 | The object/consideration must be lawful |
| 56 | Impossible act — the doctrine of frustration |
| 73 | Compensation for breach of contract (loss arising naturally) |
| 74 | Sum named in the contract (liquidated damages/penalty) — the aggrieved party gets reasonable compensation, not exceeding the named sum |
Applying the Act to the tender process
- Notice Inviting Tender (NIT) = invitation to offer; the contractor's tender = offer; the Railways' Letter of Acceptance (LOA) = acceptance.
- As soon as an unconditional LOA is issued, a binding contract comes into being — even if the formal agreement is signed later, the LOA by itself is binding (the Railways state this clearly in the LOA).
- The Railways asking for a reduced rate (counter offer) = a new offer; a contract only after the contractor accepts.
- Under Section 5 an offer can be withdrawn before acceptance — but the bid security condition (not to withdraw the offer within the validity period) is an independent agreement, so forfeiting the bid security when an offer is withdrawn within the validity period is valid (Supreme Court — NHAI vs Ganga Enterprises, 2003).
- Section 74 — the Liquidated Damages provision of the GCC rests on this; courts recognise a reasonable pre-estimated amount.
Example — looking at a tender through the Contract Act:
- 1 March — the Railways publish an NIT on IREPS (Indian Railways E-Procurement System) → this is an invitation to offer; it does not bind the Railways to award the work to anyone.
- 31 March — contractor A bids ₹4.80 crore, validity 90 days, with bid security → the bid = an offer.
- 15 April — A wants to withdraw the bid → under Section 5 the offer can be withdrawn, but the separate agreement not to withdraw within the validity period is broken → bid security forfeited.
- (If A had stayed on) 20 May — the Railways send an unconditional LOA → acceptance; the contract is complete.
- (Alternatively) the Railways said "do it for ₹4.70 crore" → this is a counter offer; a contract comes into being only if A agrees.
Section 56 — Frustration, example: A contract was made to repair an old station building, but before the work began the building was completely destroyed in a fire → the very subject of the contract no longer exists → the contract becomes void (no party at fault). A work merely becoming costlier or harder is not frustration.
1.3Article 299 of the Constitution
In simple wordsGovernment contracts are valid only if made in the name of the President, in writing, by an authorised officer.
- All contracts made in the exercise of the executive power of the Union (or a State) shall be expressed to be made by the President (or the Governor).
- Such contracts shall be executed on behalf of the President/Governor by such persons and in such manner as he may direct/authorise.
- Neither the President/Governor is personally liable, nor is the person making the contract on their behalf personally liable.
- That is why the Railways' tender notice is issued "for and on behalf of the President of India" and the agreement is signed by an authorised officer.
- The conditions of Article 299 are mandatory — a contract not complying with them is not enforceable against the Government; however, if the Government has taken the benefit, compensation can be claimed under Section 70 of the Contract Act (State of West Bengal vs B.K. Mondal, 1962).
- In the Railways, the authority to sign agreements is fixed by the MSOP/Board's letters — normally a nominated executive officer below the tender accepting authority.
1.4Finance Code Chapter VI — General Principles of Contracts
In simple wordsThe Finance Code says what must be kept in mind in every contract — clear terms, competition, financial safeguards.
- The terms of a contract must be precise and definite; there should be no room for ambiguity.
- Standard forms should be used as far as possible; departing from a standard form needs competent/finance advice.
- No contract without the sanction of the Competent Authority and the availability of funds.
- Avoid contracts with unlimited liability; no contract of indefinite duration.
- No later change in the terms of a contract that gives the contractor an extra benefit, without competent sanction and Finance Concurrence.
- General rule — a contract should be given only in the most open and public manner, after inviting tenders with adequate notice; exceptions are specified in the rules/powers.
- The officer accepting a contract must see that, if the lowest (L1) tender is rejected, the reasons are recorded in writing.
1.5Engineering Code Chapter XII — Key Paras
In simple wordsChapter XII of the Engineering Code — the detailed rules for works contracts.
Summary table
| Para | Subject |
|---|---|
| 1210 | Tender system — the primary duty of the executive is to obtain the best value for the money spent; the tender system should be adopted as far as possible |
| 1211–1214 | Circumstances for exceptions to the Open Tender (limited/single/dispensing with tenders) |
| 1214-A | Circumstances for a Single Tender |
| 1238 | Tender notice period (amended from 24.10.2018) |
| 1239 | Scrutiny/publication of the tender notice |
1.6GFR 2017 — Principles (Effect on the Railways)
In simple wordsThe GFR does not apply directly to the Railways, but the Railways also adopt its principles (transparency, competition, fairness).
- Basic principles of public procurement — transparency, competition, fairness, Economy, Efficiency and accountability.
- Code of Integrity — corrupt, fraudulent, anti-competitive and coercive practices and conflict of interest are prohibited; violation leads to rejection of the bid/debarment. The same arrangement was added to the GCC by ACS-11.
- GeM (Government e-Marketplace) for general procurement of goods and services; railway works contracts by e-Tender on IREPS.
- After the Ministry of Finance's office memorandum of 01.01.2024 (GFR Rule 171 — performance security), the Railway Board reduced the PG (Performance Guarantee) in service contracts from 10% to 5% (24.05.2024).
Exam trap
- NIT = invitation to offer; tender = offer; LOA = acceptance. Conditional acceptance = counter offer (Section 7).
- Contract = an agreement enforceable by law — Section 2(h); elements of a valid contract — Section 10.
- Liquidated Damages — Section 74; compensation for breach — Section 73; frustration — Section 56.
- Article 299 — contract in the name of the President; the President is not personally liable; the conditions are mandatory.
- GCC April 2022 — letter 27.04.2022; every ACS is prospective. Latest — ACS-11 (13.03.2026), ACS-12 (12.08.2026).
- Engineering Code — tender system 1210, Single Tender 1214-A, tender notice 1238.