Types of Contracts

Contracts & Tenders • Part 2 / 24 • Appendix-III A IREM Examination

हिंदी में पढ़ें

In this part

  1. Based on Pricing
  2. Based on Duration/Nature
  3. Based on Subject Matter
  4. Public-Private Partnership (PPP) & Other Models (Introduction)
  5. Which Type of Contract When in Railways (Practice)

First sub-topic (sample)

2.1Based on Pricing

In simple words

Based on how payment is made — Item Rate (item-wise rate), Lump Sum, or Cost + Profit, etc.

Summary Table

Type How it works Use / Feature
Item Rate Contract Contractor quotes a separate rate for every item; payment = actual quantity × item rate Most common in Railways; works involving Non-Schedule (NS) items
Percentage Rate Contract At rates of Indian Railway Schedule of Rates (SOR) — e.g., USSOR (Unified Standard Schedule of Rates) — x% above/below/at par Works with standard items; same percentage applicable to all SOR items
Lump Sum Contract A fixed amount for the entire specified work Scope of work is fully defined (e.g., standard building); quantity-risk rests with the contractor
EPC (Engineering, Procurement & Construction) Design, material procurement, and construction by a single contractor; generally fixed price (lump sum) Large projects — new line, doubling, electrification; Railway's standard EPC document
Turnkey Handing over the work in a commissioned/operational state ("Turn the key and operate") Plants / systems
Cost Plus Actual cost + fixed percentage/fee Extraordinary works with uncertain scope; difficult to control — discouraged

Item Rate vs. Percentage Rate — Difference

Point Item Rate Percentage Rate
What the contractor quotes Rate for each item A single percentage on SOR
Comparison L1 decided by item-wise grand total L1 decided by the percentage
Variation Item-wise limits Separate limit for variation in SOR items
Risk Unbalanced rates (front loading) possible in individual items Lesser imbalance
In detail

In a tender, a contractor can quote rates in two ways, and both have their own benefits and risks.

  • Item Rate — The contractor quotes a separate rate for every item; L1 (lowest) is decided by the grand total of all items. Risk — The contractor can quote a higher rate for certain items (which are to be executed early or whose quantities are likely to increase) and a lower rate for others to show a lower grand total — this is called unbalanced rates or front loading. Example — Higher rate in earthwork (which is done first) and very low in finishing — the contractor gets money early, and the risk of abandoning the work later increases.
  • Percentage Rate — The contractor quotes a single percentage on the Schedule of Rates (SOR) (e.g., 5% below or above SOR); L1 is decided on that same percentage. Since the same percentage applies to all items, imbalance is less.
  • Variation — Item-wise limits in Item Rate; separate limits for variation of SOR items in Percentage Rate.

Unbalanced rates — The contractor quotes very high rates for some items and very low for others to gain from items whose quantities are likely to increase. The Tender Committee and Member (Finance) should also examine the reasonableness of item-wise rates.

Example — How unbalanced rates cause loss: Two items in a tender — earthwork (estimated 1,000 cubic meters) and rock cutting (estimated 100 cubic meters).

Bidder Earthwork Rate Rock Cutting Rate Tender Value Actual payment when 300 cubic meters of rock turns up
X ₹300 ₹1,500 ₹4,50,000 ₹3,00,000 + ₹4,50,000 = ₹7,50,000
Y ₹240 ₹2,000 ₹4,40,000 (L1) ₹2,40,000 + ₹6,00,000 = ₹8,40,000

Y quoted a higher rate on the item whose quantity was likely to increase — despite being L1 in the tender, it ended up being ₹90,000 costlier. Therefore, the Tender Committee checks the reasonableness of item-wise rates and the realism of quantities.

Example — Percentage Rate: SOR value of work is ₹2.00 crore. If the contractor quotes "4.5% above" → Contract Value is ₹2.09 crore; if they quote "3% below" → ₹1.94 crore. Payment for every SOR item is made by applying this percentage to its SOR rate.

Full preparation in the app

All parts in Hindi + English, subject-wise MCQs and mock tests — create a free account.

Start free
‹ Previous: Legal Basis of Contracts — the Contract Act, Article 299, GFR and the CodesAll parts — Contracts & TendersNext: Modes of Tendering ›
All exams & subjects (Hindi) • Login • शिक्षक भर्ती (RPSC / REET) नोट्स • Telegram channel • गोपनीयता नीति • नियम व शर्तें • संपर्क