Engineering Code — Remaining Important Paragraphs (Chapter-wise)

Works Expenditure • Part 23 / 24 • Appendix-III A IREM Examination

हिंदी में पढ़ें

In this part

  1. Practical Rules Related to Surveys (Chapter II and VI)
  2. Estimates — Remaining Paragraphs (Chapter VII)
  3. Execution of Works — Remaining Paragraphs (Chapter XI)
  4. Contracts — Chapter XII of Engineering Code
  5. Measurement, Bills and Initial Records — Remaining Paragraphs (Chapter XIII)
  6. Divisional Accounts — Imprest, Stores, Materials-at-Site, Tools and Registers (Chapter XIV)
  7. Opening of New Lines and Handing Over to Open Line (Chapter XVI)
  8. Completion — Precise Rules of Engineering Code (Chapter XVII)
  9. Defense Works, Road-bridges and Quarries (Chapter XVIII)
  10. Land Payments and Other Land-related Rules (Chapter IX and X)

First sub-topic (sample)

In simple words

Key paragraphs of the Engineering Code (E-Code, Revised Edition 1982, Fourth Reprint — including ACS 61 dated 21.10.2022) have appeared in previous chapters. Here are the paragraphs that were left out so far — practical rules for surveys, Chapter XII on contracts, Divisional Accounts (Chapter XIV), Opening of New Lines (XVI), Limits of Closing (XVII), and rules for Defense/Road-bridges (XVIII). The rules of each paragraph are in plain language; they may be asked in exams along with the paragraph number.

23.1Practical Rules Related to Surveys (Chapter II and VI)

Para Rule
253 Notification in the Local Government Gazette as per Section 4 of the Land Acquisition Act before commencing survey work.
254 General Survey Sanction from the Railway Board does not grant the right to interfere with the property of any person or institution; permission from the Commanding Officer is required for the survey team to enter a cantonment, fort, or military post.
255 If damage to private property is unavoidable, the engineer should provide compensation to the owner, if possible, on the spot before the damage occurs; in case of a dispute, it shall be decided by the Local Civil Authority.
256, 1125 Avoid interference with religious buildings — no religious building shall be destroyed without the full and free consent of the stakeholders and the concurrence of the principal civil authority; protection of archaeological remains.
259 If the line is near any military post, camping ground, rifle range, or cantonment, the location should be fixed in consultation with Local Military Authorities.
266 Send the project report, construction estimate, and index plan (1 cm = 0.5 km, showing all waterways and level crossings) directly to the State Government.
267 Quarterly Progress Report of the survey (Form E-267) — starting from the quarter in which the survey is sanctioned; it must reach the Railway Board before the 25th of the month following the quarter (31st March / 30th June / 30th September / 31st December).
268 Before a project for line capacity, terminal, or repair facility, ask for the requirements of the User Department; a work study team is required before proposals for new marshalling yards/terminals.
630 If the Board's budget orders are not received by the start of the financial year, expenditure on works in progress from the previous year can continue — against the allocation to be received later.
631 If there is a reduction from the estimate sent in the budget order, limit the expenditure immediately to the allocated amount.
633 Planning of surveys in advance — separate details of ongoing and new surveys along with the Works Programme to the Board; if the same survey was proposed earlier, its result should also be provided.
634 Cost of survey and preliminary investigation from Revenue (Demand No. 2 in the Code — now a single Demand No. 85); as per the Code, prior approval of Parliament is required for surveys exceeding ₹1 lakh; on project formation, survey expenditure is transferred to Capital/Appropriate Head (credit to Revenue), regardless of the year the expenditure occurred.
Exam trap

Quarterly report of the survey — to the Board by the 25th of the following month. Survey expenditure is initially Revenue, and on project formation, it becomes Capital — expenditure of previous years is also transferred.

Full preparation in the app

All parts in Hindi + English, subject-wise MCQs and mock tests — create a free account.

Start free
‹ Previous: Quick Revision — Numbers, Dates and Exam TrapsAll parts — Works ExpenditureNext: Question-bank digest — works accounts, estimates, plan heads, budget classification, appropriation accounts, general books ›
All exams & subjects (Hindi) • Login • शिक्षक भर्ती (RPSC / REET) नोट्स • Telegram channel • गोपनीयता नीति • नियम व शर्तें • संपर्क