22.1Numbers at a Glance
In simple wordsConstruction work questions mostly revolve around limits, percentages and para-numbers — everything consolidated below.
Summary Table
| Subject | Number |
|---|---|
| Types of Estimate | 7 (A D S R P C C) |
| Validity of Sanction | 5 years; if work does not start, lapses in 2 years |
| Validity of Umbrella | 2 years (Budget Year + 1) |
| Pink Book / LAW Book | ₹50 crore and above / Less than ₹50 crore |
| Permissible Cost | PC = C × N − TF |
| Contingent Expenditure | Code 3% (727-E); Current 1% (28.12.2022) |
| Departmental Charges Limit | Civil 5.33%, Track Renewal 1.53%, Electrical 7.16%, S&T (Signal and Telecommunication) 10.05%, Mechanical 4.93% |
| ERW (Environment Related Works) / Sports Fund | 0.5% (PH 11,14,15,30,42) / 0.1% (except PH 17, 31) |
| Deposit Works Departmental Charges | 12.5% |
| Private Siding Overhead | Railway 12.5%, Party 6.25%, Consultant 4% |
| Partial Waiver of Departmental Charges in Siding | GM (General Manager) up to ₹10 lakh |
| RE — GM (General) | Cost escalation Full; Others 20%; MM ₹2.5 crore |
| RE — M&P (Machinery and Plant) | Cost escalation 100% or ₹2 crore (whichever is less); Others 20% or ₹50 lakh (whichever is less) |
| OOT (Out of Turn) — GM | ₹2.5 crore/case, ₹25 crore/year (Non-safety); Safety — No limit, complete in 8 months |
| GM (08.05.2024) | PH 16/30/31/32 (Plan Head) ₹50 crore; PH 53 ₹20 crore; PH 29/33/35/36/41/42 ₹10 crore; PH 17/18/51/64/65 ₹5 crore |
| DRM (08.05.2024) | PH 16/29/30/33/36/42/53 ₹5 crore |
| Project Sanction | ≤₹100 crore CRB&CEO; ≤₹500 crore Minister of Railways; ≤₹1000 crore Ministry of Railways (EBR — Extra Budgetary Resources); >₹1000 crore CCEA (Cabinet Committee on Economic Affairs) |
| NPG (Network Planning Group) / ITLA | More than ₹500 crore / ₹500 crore or more (Technical) |
| DPR (Detailed Project Report) Compulsory | New project costing more than ₹50 crore |
| MB (Measurement Book) Preserved | 10 years |
| CMB Provisional Payment | 75% |
| Ballast Challan | 4 copies |
| Contractor Account Balance → Deposit-Miscellaneous | After 1 month of final certificate |
| TDS (Tax Deducted at Source — Contractor) | 1% / 2% — Income Tax Act 2025 Section 393(1) (previously 194C) |
| GST (Goods and Services Tax) TDS / BOCW (Building and Other Construction Workers) Cess | 2% (above ₹2.5 lakh) / 1% |
| ROB (Road Over Bridge) Eligibility (Traditional) | 1 lakh TVU (Train Vehicle Unit), 50:50 |
| Sanctioned ROB/RUB (01.07.2025) | 4,430, approx. ₹1,03,492 crore |
| Land Lease (2022) | 1.5%, 35 years |
| GCT (Gati Shakti Multi-Modal Cargo Terminal — January 2026) | 306 sanctioned, 118 operational |
| Projects Sanctioned in 2025-26 | 100, approx. ₹1.53 lakh crore |