In simple wordsA work's life cycle is — survey → estimate and sanction → tender and contract → measurement in MB and payment → control in the works register → completion report. The facts for each stage and the budget/account heads are below.
1Surveys and project appraisal
| Survey | Purpose |
|---|---|
| Reconnaissance — the first | technical feasibility |
| Traffic | traffic projections (basis of earnings estimate) |
| Preliminary | close estimate and probable cost |
| Final location (FLS) | selecting the alignment |
- "Accounts survey" is not a survey; surveys fall in 4 classes; pre-investment appraisal of major projects is through surveys; detailed traffic and engineering surveys for new line/GC/doubling above Rs 5 crore; survey expenditure — Demand 82 (old 2) (question bank).
- DCF (Discounted Cash Flow) — minimum ROR 10% (question bank); ROR not applicable to passenger amenities and safety; post-project appraisal — productivity test; "financial justification" is not an appraisal technique.
- Average annual cost of service = operation + maintenance + depreciation; assessed from traffic costing data; lives (question bank) — concrete sleepers A/B routes 35, electric loco 35, bridge masonry 100, CCTV 8, microwave 12–15, walkie-talkie 5–8 years.
- No financial justification needed — unavoidable safety, passenger amenities, labour welfare except housing; additional rolling stock — justified on general growth of traffic; line capacity = trains per day on a section.