Railway Land — Acquisition, Management, Leasing Policy and Accounting

Works Expenditure • Part 19 / 24 • Appendix-III A IREM Examination

हिंदी में पढ़ें

In this part

  1. Rule Sources
  2. Main Principles
  3. Land Allocation and Accounting
  4. Land Management
  5. Land Leasing Policy for PM Gati Shakti (Cabinet Decision 07.09.2022)
  6. A Railway Land Management Policy — Master Circular 2021/LML/25/5 (07.10.2022)
  7. Lease versus Licence — Legal Difference
  8. Way Leave / Easement Charges

First sub-topic (sample)

19.1Rule Sources

In simple words

Where the rules for railway land are located.

Sequence of acquisition in a Special Railway Project (Chapter IVA — in simple terms):

  1. The Central Government notifies the project as a "Special Railway Project" and a notification of intention to acquire land (Section 20A) is issued.
  2. Stakeholders can submit objections within a specified period (30 days); the competent authority conducts a hearing.
  3. After the disposal of objections, the declaration of acquisition (Section 20E) is issued — upon publication, the land vests in the Central Government (free from all encumbrances).
  4. The competent authority determines compensation (including compensation/rehabilitation criteria of the 2013 Act since 2015); if the amount is not accepted, an Arbitrator appointed by the Centre decides.
  5. Deposit/payment of amount → Possession of land → Construction.

Summary Table

Source Subject
Engineering Code Chapter VIII — Rules for Land Acquisition 801 Applicability, 802 How land is to be acquired, 855 Incidental charges, 856 Land for quarries, 857 Forest land
Engineering Code Chapter IX Procedure for land acquisition
Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (RFCTLARR) General acquisition; replaced the Land Acquisition Act of 1894
Railways Act, 1989 — Chapter IVA (Sections 20A to 20P) — inserted by Railways (Amendment) Act, 2008 Land acquisition for "Special Railway Projects" — Central Government declares the project by Notification; Competent Authority, determination of compensation
Fourth Schedule of RFCTLARR 13 Central Acts including the Railways Act — compensation and rehabilitation provisions of the 2013 Act also applicable to these from 2015
In detail

Land acquisition for railways can take place through two legal routes, and the rules for compensation are now identical in both.

  • Engineering Code — Chapters VIII and IX — Railway's own rules and procedures: applicability, how land is to be acquired, incidental charges, quarry and forest land.
  • General Route — RFCTLARR Act, 2013 — Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement — which replaced the old Land Acquisition Act of 1894.
  • Special Route — Chapter IVA of the Railways Act (Sections 20A–20P) — Introduced by the 2008 amendment; the Central Government declares a project as a "Special Railway Project" through a notification, and land is then acquired through a expedited procedure.
  • Convergence of Both — Fourth Schedule — The compensation and rehabilitation provisions of the 2013 Act also apply to 13 Central Acts including the Railways Act from 2015 — meaning even if land is acquired through the special route, the landowner will receive fair compensation.
Full preparation in the app

All parts in Hindi + English, subject-wise MCQs and mock tests — create a free account.

Start free
‹ Previous: Level Crossings (LC) and ROB/RUB — Policy, Cost-Sharing and AccountingAll parts — Works ExpenditureNext: Completion of Work — Completion Estimate, Completion Report, Asset Register and Post-Project Appraisal ›
All exams & subjects (Hindi) • Login • शिक्षक भर्ती (RPSC / REET) नोट्स • Telegram channel • गोपनीयता नीति • नियम व शर्तें • संपर्क