Completion of Work — Completion Estimate, Completion Report, Asset Register and Post-Project Appraisal

Works Expenditure • Part 20 / 24 • Appendix-III A IREM Examination

हिंदी में पढ़ें

In this part

  1. Completion Estimate vs. Completion Report
  2. Completion Report
  3. Asset Register — 1720-E
  4. Post-project Appraisal
  5. Handing over and Utilization of Asset
  6. Example

First sub-topic (sample)

20.1Completion Estimate vs. Completion Report

In simple words

Completion Estimate = Final cost; Completion Report = Formal statement of the completed work.

Summary Table

Point Completion Estimate (713-E) Completion Report (1704–1705-E)
When Near completion of the project — estimate of final cost After the work is completed and all charges and credits are booked in the accounts
Form E-713 Prescribed form
What it shows Sanctioned amount, expenditure so far, commitments, further anticipated expenditure, total estimated cost, variation Actual cost vs. Final Sanctioned Estimate
Place Takes the place of the Construction Estimate Closes the financial chapter of the work
In detail

Both have similar names, but the Completion Estimate and Completion Report are prepared at different times of the work and perform different functions.

  • Completion Estimate (713-E) — Prepared when the project is near completion; it is an estimate of what the final cost will be — sanctioned amount, expenditure so far, commitments, further anticipated expenditure, and total estimated cost. It takes the place of the construction estimate.
  • Completion Report (1704–1705-E) — After the work is completed and all charges and credits have been booked; it is a comparison of the actual cost with the final sanctioned estimate — and closes the financial chapter of the work.

Summary: Completion Estimate = "How much it will cost" (Future); Completion Report = "How much it cost" (Past).

Full preparation in the app

All parts in Hindi + English, subject-wise MCQs and mock tests — create a free account.