Types of On-cost, Costing Methods, Outturn Statement, WMS Budget and Workshop Planning

Workshop Accounts • Part 9 / 14 • Appendix-III A IREM Examination

हिंदी में पढ़ें

In this part

  1. Basic ideas of cost
  2. Types of on-cost
  3. Production documents — Route Card, Tools & Plant
  4. Outturn Statement and debits to WMS
  5. WMS budget and appropriation
  6. Workshop planning, plant & machinery and maintenance

First sub-topic (sample)

1Basic ideas of cost

In simple words

Cost is expenditure that can be charged to a product or service. Costing means classifying expenditure, charging it to a job, and working out the cost per unit.

Methods of costing — where each is used

Method Where used Identification
Job costing Spares/components made in zonal workshops Separate cost for each work order; starts from standard estimates (material, labour, on-cost)
Batch costing Manufacture of rolling stock in production units Cost of a batch of identical units ÷ number
Process costing Continuous processes Process cost sheet — direct labour, direct material, fuel, indirect material, on-cost
Unit Repair Cost (URC) POH (Periodical Overhaul) POH cost per engine/coach/wagon (sub-topic 2)
In detail

Different methods of costing suit different kinds of workshop activity. Job costing is used for spares and components made in zonal workshops; each work order is costed separately, starting from standard estimates of material, labour and on-cost. Batch costing is used in production units, where identical units such as coaches are made in batches; the cost of the batch is divided by the number of units.

Process costing is used for continuous processes, with a process cost sheet covering direct labour, direct material, fuel, indirect material and on-cost. For POH, the Unit Repair Cost gives the overhaul cost per engine, coach or wagon. The method follows the nature of the output: individual jobs, batches, a continuous process, or repeated overhauls.

  • Marginal costing is a decision technique (sub-topic 4), not a "method" of costing.
  • Revised POH costing system — identify cost centres for POH and production activities; the aim is the POH cost per engine/coach/wagon.
  • Cost sheet — prepared by the Production Control Organisation (PCO) → internal check in the Workshop Accounts Office (WAO — Workshop Accounts Officer).
Example (batch costing)

A production unit built a batch of 50 coaches — material ₹60 crore, labour ₹10 crore, on-cost ₹5 crore = ₹75 crore → ₹1.5 crore per coach. A zonal workshop making spares would instead work out a separate (job) cost for each work order.

Full preparation in the app

All parts in Hindi + English, subject-wise MCQs and mock tests — create a free account.

Start free
‹ Previous: Estimates for Works, Outside Work, Hire Charges and Completion ReportsAll parts — Workshop AccountsNext: Machinery & Plant Programme, Types of Maintenance and Workshop Modernisation ›
All exams & subjects (Hindi) • Login • शिक्षक भर्ती (RPSC / REET) नोट्स • Telegram channel • गोपनीयता नीति • नियम व शर्तें • संपर्क