Estimates for Works, Outside Work, Hire Charges and Completion Reports

Workshop Accounts • Part 8 / 14 • Appendix-III A IREM Examination

हिंदी में पढ़ें

In this part

  1. Works in the workshop and their estimates (Paras 701–711)
  2. Work for outside parties (Paras 712–714)
  3. Hire charges (Paras 731–733)
  4. Completion reports and productivity review

First sub-topic (sample)

1Works in the workshop and their estimates (Paras 701–711)

In simple words

It is not practical to prepare an estimate every time for day-to-day repairs — they are done without a formal order. But a new asset, special work or work for an outside party needs a detailed estimate.

Work Estimate
Regular repairs and maintenance (old Demands 05, 06, 07 — locos, carriages and wagons, plant) Without a formal order or estimate
Works of a capital or special nature; work for outside parties, other railways or government bodies Detailed estimate required
New asset (702–706) Abstract estimate, rate analysis, rate of return; vetting by associate finance; detailed estimate to the WAO (Workshop Accounts Officer); estimates for rolling stock/machinery include freight, customs duty, erection, on-cost etc.
Replacement (707–708) Description of the asset, age, original capital cost, value of released material
In detail

Not every workshop job needs an estimate. Regular repairs and maintenance of locos, carriages and wagons, and plant — the old Demands 05, 06 and 07 — are done without a formal order or estimate, because they are the workshop's routine business.

A detailed estimate is needed for works of a capital or special nature and for work done for outside parties, other railways or government bodies. A new asset (paras 702–706) needs an abstract estimate, a rate analysis and a rate of return, vetted by associate finance, with the detailed estimate sent to the Workshop Accounts Officer. A replacement (paras 707–708) must describe the asset, its age, its original capital cost and the value of material released, so that the cost can be split correctly between DRF and capital.

Reconditioning versus replacement

Solved example

An old machine —

  • Reconditioning: ₹6 lakh, after which it runs 4 more years, annual maintenance ₹1 lakh → average annual cost = 6 ÷ 4 + 1 = ₹2.5 lakh.
  • Replacement: new machine ₹30 lakh, runs 15 years, annual maintenance ₹0.5 lakh → 30 ÷ 15 + 0.5 = ₹2.5 lakh. Both are equal; in such a case reconditioning gets priority (less capital, from revenue). If after reconditioning it ran only 2 years → 6 ÷ 2 + 1 = ₹4 lakh → replacement is better. (This is a simple comparison; interest cost can also be added.)

Released material and validity

Full preparation in the app

All parts in Hindi + English, subject-wise MCQs and mock tests — create a free account.

Start free
‹ Previous: Workshop Manufacture Suspense (WMS)All parts — Workshop AccountsNext: Types of On-cost, Costing Methods, Outturn Statement, WMS Budget and Workshop Planning ›
All exams & subjects (Hindi) • Login • शिक्षक भर्ती (RPSC / REET) नोट्स • Telegram channel • गोपनीयता नीति • नियम व शर्तें • संपर्क