LatestThe clause numbers below are of GCC (General Conditions of Contract) April 2022 Part-II — up to ACS-11 (13.03.2026) and ACS-12 (12.08.2026).
1Security Deposit and Performance Guarantee (Clause 16)
In simple wordsTwo separate securities are taken from the contractor — SD (5% of the contract value, gradually from bills) and PG (a guarantee of proper completion of the work, at the very start).
| Item | Provision |
|---|---|
| Security Deposit (SD) | 5% of the contract value (not of the tender value); the successful bidder's bid security forms part of the SD; recovery — the full amount in cash/TDR before the first On-account Bill, or 6% from every bill; for contracts of ₹50 crore or more, a bank guarantee bond is also accepted; no interest on SD |
| Refund of SD | After all three — (1) final payment; (2) the final supplementary agreement or a "no claim" certificate; (3) a maintenance certificate after the maintenance period |
| Performance Guarantee (PG) | 5% of the contract value; within 21 days of the LOA (Letter of Acceptance); returned after the completion certificate and "no claim"; if the contract period is extended, the validity of the PG must also be extended; APG (Additional Performance Guarantee) on very low bids; in service contracts PG is 5% from 24.05.2024 |
| On default | On termination of the contract, SD is forfeited and PG encashed; the total amount withheld from a defaulting contractor (including PG) is not more than 10% of the total contract value |
Clause 16 of the GCC provides two separate securities. The Security Deposit is 5 per cent of the contract value (not the tender value). The successful bidder's bid security counts towards it, and the rest is either paid in full in cash or TDR before the first on-account bill or recovered at 6 per cent of every bill; for contracts of ₹50 crore or more a bank guarantee is also accepted. No interest is paid on SD. It is refunded only after all three of the following: final payment, the final supplementary agreement or a "no claim" certificate, and a maintenance certificate after the maintenance period.
The Performance Guarantee, also 5 per cent, is given within 21 days of the LOA and returned after the completion certificate and "no claim"; if the contract period is extended, its validity must be extended too. In service contracts the PG is 5 per cent from 24.05.2024. On termination for default, the SD is forfeited and the PG encashed, but the total withheld from the contractor, including the PG, is capped at 10 per cent of the contract value.
RememberSD is 6% per bill so that the 5% amount is recovered by the time about 83% (5 ÷ 6) of the work has been billed.