PVC, Advances to Contractors, Measurements and Bills

General Expenditure • Part 8 / 10 • Appendix-III A IREM Examination

हिंदी में पढ़ें

In this part

  1. Price Variation Clause — PVC (Clause 46A)
  2. Advances to contractors (Clause 46(4))
  3. Measurements, bills and final payment
  4. Full solved example — the final bill

First sub-topic (sample)

1Price Variation Clause — PVC (Clause 46A)

In simple words

In large, long-running contracts, prices of material, labour and fuel change midway. PVC raises or lowers the payment according to that change — if prices rise the contractor gets more; if they fall the Railway recovers.

Point Provision
Applies to Contract agreement value (not tender value) of ₹2 crore or more; not to zonal contracts and AMCs
Components Labour, material, fuel — and steel and cement separately; no variation on the 15% fixed component
Indices Prescribed official indices (Wholesale Price Index, Consumer Price Index for labour, etc.), on the basis of the quarterly average; compared with the base month (defined in the tender)
Direction Both ways — rises go to the contractor; falls are recovered by the Railway
During the extended period Delay due to the Railway — PVC as usual; delay due to the contractor — no benefit if prices rise (indices of the original completion date); if they fall, the Railway benefits
Material supplied by the Railway (Free or at a fixed rate) outside PVC
In detail

The Price Variation Clause (46A) adjusts payments for changes in input prices during the contract. It applies to contracts whose agreement value is ₹2 crore or more, but not to zonal contracts and AMCs. The price is split into components — labour, material, fuel, and steel and cement separately — while a 15 per cent fixed component never varies.

Each component moves with a prescribed official index, such as the Wholesale Price Index or the Consumer Price Index for labour, using the quarterly average compared with the base month in the tender. Variation works both ways: rises are paid to the contractor and falls are recovered. During an extension caused by the Railway, PVC runs as usual; if the contractor caused the delay, he gets no benefit from rising prices (indices of the original completion date apply), but the Railway still benefits if prices fall. Material supplied by the Railway is outside PVC.

Solved example (PVC — principle for the material component)

Value of work in a bill ₹1 crore; material component as per contract 40%; the material index for that quarter rose from 150 in the base month to 162 (+8%).

Adjustment for the material component = 1,00,00,000 × 40% × (162 − 150) ÷ 150 = 40,00,000 × 0.08 = ₹3,20,000 extra to the contractor.

(The actual formula and weights of components come from the contract's PVC conditions; no adjustment on the 15% fixed part.)

Full preparation in the app

All parts in Hindi + English, subject-wise MCQs and mock tests — create a free account.

Start free
‹ Previous: GCC-2022 — Securities, Sub-contracting, Time, LD, Bonus and Variation in QuantitiesAll parts — General ExpenditureNext: Imprest, Materials at Site, Deposit Works, Losses and Accounts Inspection ›
All exams & subjects (Hindi) • Login • शिक्षक भर्ती (RPSC / REET) नोट्स • Telegram channel • गोपनीयता नीति • नियम व शर्तें • संपर्क