1Price Variation Clause — PVC (Clause 46A)
In simple wordsIn large, long-running contracts, prices of material, labour and fuel change midway. PVC raises or lowers the payment according to that change — if prices rise the contractor gets more; if they fall the Railway recovers.
| Point | Provision |
|---|---|
| Applies to | Contract agreement value (not tender value) of ₹2 crore or more; not to zonal contracts and AMCs |
| Components | Labour, material, fuel — and steel and cement separately; no variation on the 15% fixed component |
| Indices | Prescribed official indices (Wholesale Price Index, Consumer Price Index for labour, etc.), on the basis of the quarterly average; compared with the base month (defined in the tender) |
| Direction | Both ways — rises go to the contractor; falls are recovered by the Railway |
| During the extended period | Delay due to the Railway — PVC as usual; delay due to the contractor — no benefit if prices rise (indices of the original completion date); if they fall, the Railway benefits |
| Material supplied by the Railway | (Free or at a fixed rate) outside PVC |
The Price Variation Clause (46A) adjusts payments for changes in input prices during the contract. It applies to contracts whose agreement value is ₹2 crore or more, but not to zonal contracts and AMCs. The price is split into components — labour, material, fuel, and steel and cement separately — while a 15 per cent fixed component never varies.
Each component moves with a prescribed official index, such as the Wholesale Price Index or the Consumer Price Index for labour, using the quarterly average compared with the base month in the tender. Variation works both ways: rises are paid to the contractor and falls are recovered. During an extension caused by the Railway, PVC runs as usual; if the contractor caused the delay, he gets no benefit from rising prices (indices of the original completion date apply), but the Railway still benefits if prices fall. Material supplied by the Railway is outside PVC.
Solved example (PVC — principle for the material component)Value of work in a bill ₹1 crore; material component as per contract 40%; the material index for that quarter rose from 150 in the base month to 162 (+8%).
Adjustment for the material component = 1,00,00,000 × 40% × (162 − 150) ÷ 150 = 40,00,000 × 0.08 = ₹3,20,000 extra to the contractor.
(The actual formula and weights of components come from the contract's PVC conditions; no adjustment on the 15% fixed part.)