1Life-cycle of a work
In simple wordsEvery work needs three "yes"es — "this work is to be done" (administrative approval), "with this design and at this cost" (technical sanction), and "there is money for it" (funds). Without all three, work does not start.
- Need / survey;
- Abstract Estimate → included in the Works Programme (Pink Book) = administrative approval;
- Detailed Estimate → vetting by Accounts → Technical Sanction;
- Tender and contract;
- Execution — measurement, bills, register of works;
- Completion → Completion Report → asset register.
| Term | Meaning |
|---|---|
| Administrative approval | "This work is to be done" — acceptance of the need and the cost |
| Technical Sanction | "With this design and at this cost" — on the detailed estimate |
| Funds | Budget grant, or a sanctioned re-appropriation |
| Umbrella works | A lump-sum provision in the Pink Book for small works, under which the GM (General Manager) sanctions small works |
| Out-of-turn works | Outside the budget, sanctioned by the Board for urgent needs; included in the next budget |
A work goes through distinct approvals before money can be spent on it. Administrative approval says that the work is needed and accepts its broad cost. Technical sanction says that it will be done with a particular design at a particular cost, and is given on the detailed estimate. Neither is enough without funds, which come from the budget grant or a sanctioned re-appropriation.
Two special arrangements exist for flexibility. Umbrella works are lump-sum provisions in the Pink Book for small works, under which the General Manager sanctions individual small works during the year. Out-of-turn works are urgent works not in the budget, which the Board sanctions and which are then included in the next budget. The sequence to remember is: need accepted, design and cost sanctioned, money provided.
Exam trapWork does not start without Technical Sanction and funds — merely appearing in the Pink Book (administrative approval) is not enough.