Economic Appraisal — FIRR, EIRR and MEIRR

Associated Finance & Appraisal • Part 16 / 21 • Appendix-III A IREM Examination

हिंदी में पढ़ें

In this part

  1. Financial vs. Economic Appraisal
  2. Economic Appraisal in Finance Code — Para 235, 235A
  3. Modified Economic Internal Rate of Return (MEIRR) — 2022
  4. Traditional Criteria of Government of India (Department of Expenditure)
  5. Social Cost-Benefit Analysis (SCBA) — Basics

First sub-topic (sample)

16.1Financial vs. Economic Appraisal

In simple words

Financial Appraisal = How much money the Railway will get; Economic Appraisal = Total benefit to the entire country/society.

Why are both different — A new line for the Railways is "profitable" only if its expenses are covered by the income from tickets and freight (FIRR — Financial Internal Rate of Return). But from that same line, truck congestion on the road decreases, passengers save hours, accidents and pollution reduce — these benefits do not go into the Railway's chest, but the country receives them (EIRR — Economic Internal Rate of Return). The government looks at both: FIRR tells how much burden will fall on the Railways, EIRR tells whether it is appropriate for the country to bear that burden.

Example

An 80 km new line in a hilly area — cost ₹2,000 crore.

Benefit (Annual, Steady State) In FIRR In EIRR
Fare-Freight Income − Operating Cost ₹110 crore ₹110 crore
Value of travel-time savings of passengers — ₹95 crore
Reduction in road accidents — ₹30 crore
Savings in fuel and road maintenance of trucks — ₹45 crore
  • In FIRR, only ₹110 crore is included → return approximately 3–4% (much less than 10%) → financially unremunerative.
  • In EIRR, total ₹280 crore (also after removing taxes/duties from cost) → return more than 12% → economically justified.
  • Such a project falls under the "Socially Desirable" category and is often approved based on MEIRR, usually with cost-sharing from the State Government.

Summary Table

Aspect Financial (FIRR) Economic (EIRR)
Full Name Financial Internal Rate of Return Economic Internal Rate of Return
Perspective Implementing Agency (Railways) — Actual cash inflows/outflows Society/Nation — Total economic benefit
Costs Only Financial — Capital, Operating, Maintenance Financial costs + Social/Environmental Externalities
Benefits Only Monetary — Revenue, Savings Monetary + Non-monetary — Time savings, reduction in pollution, reduction in accidents etc.
Taxes & Subsidies Included Excluded — These are transfers, not actual resource costs
Prices Market Price Shadow prices — Where market price does not reflect actual economic cost
Discount Rate Cost of capital/expected return Social Discount Rate (usually lower)
Example FIRR 10% from ticket-revenue EIRR 18% including passenger time savings, pollution reduction
Full preparation in the app

All parts in Hindi + English, subject-wise MCQs and mock tests — create a free account.

Start free
‹ Previous: Comparison of Alternatives, Replacement and Second-Hand Value (Para 234, 236–242)All parts — Associated Finance & AppraisalNext: Framework for Appraisal and Sanction of Projects ›
All exams & subjects (Hindi) • Login • शिक्षक भर्ती (RPSC / REET) नोट्स • Telegram channel • गोपनीयता नीति • नियम व शर्तें • संपर्क