9.1Components of an Estimate
In simple wordsParts of an Estimate — Quantities, rates, Contingent Expenditure, Departmental Charges, etc.
Summary Table
| Component | Para | Description |
|---|---|---|
| Report and Justification | 722-E | Why the work is necessary, alternatives, Financial Propriety, benefits |
| Specification | 724-E | Standard specifications are kept by the orders of GM (General Manager); reference of their serial number in the estimate |
| Rates | 726-E | Schedule of Rates, Last Accepted Rates (LAR), rate analysis |
| Contingencies | 727-E | Provision for unforeseen items (below) |
| Schedule of Rates (SOR) | 729–730-E | Every open line division maintains a schedule of rates |
| Covering Letter | 731-E | Estimate beyond GM's power to the Board with a covering letter — existing sanction and allocation, outlay up to the end of the previous year, funds in the current year's budget, etc. |
| Indirect Charges | 717-E | Adjustment of Foreign Service Contribution (FSC) between open line and construction stopped w.e.f. 1.4.1992; construction accounts do not include Leave Salary and Pension Contribution |
In detail
An estimate is not merely a figure of cost — it has multiple components, and every component answers some question of the sanctioning authority.
- Report and Justification (722) — "Why is the work necessary?" — alternatives, financial propriety, and benefits.
- Specification (724) — "By what standard will it be built?" — standard specifications are kept by the orders of the General Manager; only the reference to their serial number is given in the estimate.
- Rates (726, 729–730) — "Where were the rates taken from?" — Schedule of Rates (SOR — maintained by every open line division), Last Accepted Rates (LAR), or rate analysis.
- Contingencies (727) — Provision for unforeseen items.
- Covering Letter (731) — For estimates beyond the General Manager's powers to the Board — with details of existing sanction, expenditure so far, and funds in the current budget.
- Indirect Charges (717) — Adjustment of Foreign Service Contribution between open line and construction stopped from 1.4.1992; and construction accounts do not include leave salary and pension contribution.