Estimates — 1: Necessity and Seven Types (Engineering Code Chapter VII)

Works Expenditure • Part 8 / 24 • Appendix-III A IREM Examination

हिंदी में पढ़ें

In this part

  1. When is an Estimate Necessary (701-E)
  2. Seven Types of Estimates — Mnemonic "A D S R P C C"
  3. Abstract Estimate — 702-E
  4. Detailed Estimate — 703–704-E
  5. Supplementary Estimate — 707-E
  6. Revised Estimate — 708-E
  7. Project Abstract and Construction Estimate — 709–712-E
  8. Completion Estimate — 713-E

First sub-topic (sample)

8.1When is an Estimate Necessary (701-E)

In simple words

Before starting any work, an estimate showing how much cost and under which head is required.

Work Estimate necessary when cost
Renewals/replacements chargeable to DRF (Depreciation Reserve Fund) / DF (Development Fund) etc. Exceeds ₹50,000
Renewals chargeable to Revenue Exceeds ₹2 lakh
Reconditioning Exceeds ₹1 lakh
Repairs chargeable to Revenue Exceeds ₹5 lakh
Single housing unit Exceeds ₹20,000
In detail

Making an estimate for every petty work is not practical — therefore, 701-E sets limits above which an estimate is compulsory.

  • Renewals/replacements chargeable to DRF/DF etc. — Exceeds ₹50,000.
  • Renewals chargeable to Revenue — Exceeds ₹2 lakh.
  • Reconditioning — Exceeds ₹1 lakh.
  • Repairs chargeable to Revenue — Exceeds ₹5 lakh.
  • Single housing unit — Exceeds ₹20,000.

Rationale: Control on works financed from funds (DRF/DF) is strict (lower limit), whereas routine repairs have greater latitude (higher limit) — because repairs occur repeatedly and making an estimate every time would halt the work.

  • For works up to these limits, a Detailed Estimate is not required, but a rough estimate is kept in record with the Executive Engineer. Why Estimates? An estimate is a tool to think before spending — how much money it will cost, under which head, from which fund, and whether the expenditure is justified. A Sanctioned Estimate becomes the benchmark for subsequent tendering, bills, and expenditure control.

Example — Limits:

  • Replacement of a pump chargeable to DRF costing ₹40,000 → Estimate not necessary (only rough estimate in record); ₹60,000 → Estimate necessary.
  • Repair of a building chargeable to Revenue costing ₹4 lakh → Estimate not necessary; ₹6 lakh → Estimate necessary.
Full preparation in the app

All parts in Hindi + English, subject-wise MCQs and mock tests — create a free account.

Start free
‹ Previous: Umbrella Works, Lump sum Works and Out-of-Turn WorksAll parts — Works ExpenditureNext: Estimate — 2: Subject Matter, Rates, Contingent Expenditure and Departmental Charges ›
All exams & subjects (Hindi) • Login • शिक्षक भर्ती (RPSC / REET) नोट्स • Telegram channel • गोपनीयता नीति • नियम व शर्तें • संपर्क