13.1Modes of Execution
In simple wordsWays of getting works executed — through contract, departmentally (through own labour), or through PSU/agency.
Types of contracts — same work, different payment methods: Suppose an earthwork embankment of 1,000 cubic metres is to be constructed.
- Item rate — Contractor quotes a rate per cubic metre (e.g., ₹300); payment = Actual measured quantity × rate → If 1,050 cubic metres are built, ₹3,15,000. Risk of variation in quantity lies with the Railway.
- Percentage on SOR — Contractor bids "+5%" or "-3%" on the rates of the Unified Standard Schedule of Rates (USSOR); payment = SOR rate × (1 ± percentage) × measured quantity.
- Lump sum — A fixed amount for the entire defined work; if drawings/scope do not change, the risk of quantity lies with the contractor.
- EPC (Engineering, Procurement and Construction) — Design, material procurement, and construction all by the contractor; payment on milestones (e.g., "bridge foundation completed"); speed and single-point responsibility in major projects.
Summary Table
| Mode | Description |
|---|---|
| Departmental | Railway's own staff/muster roll labourers, own materials — now limited (maintenance, emergencies) |
| Through Contract | Most works — E-tender (IREPS — Indian Railways E-Procurement System), on GCC (General Conditions of Contract) terms; Item rate / Percentage on SOR, Lump sum, EPC (Engineering, Procurement and Construction — major projects) |
| Through Railway PSUs/Agencies | RVNL (Rail Vikas Nigam Limited), IRCON, RITES (Rail India Technical and Economic Service), DFCCIL (Dedicated Freight Corridor Corporation of India Limited) etc. — on behalf of the Ministry of Railways |
| Deposit Works | At the cost of an external party (page 17) |
- Open Line Organization — Maintenance and renewal of assets; Construction Organization — New projects, under CAO/C (101-E); Gati Shakti Units in divisions.