4.1Tender Notice Period (Engineering Code Para 1238 — Amended w.e.f. 24.10.2018)
In simple wordsThe minimum number of days between the issuance of the tender notice and the opening of the tender — so that everyone gets preparation time.
Example — Dates: An e-tender of ₹1.5 crore was uploaded on IREPS (Indian Railways E-Procurement System) on January 2.
- General rule (21 days) → Tender should open on January 23 or later; validity of offer = 3 × 21 = 63 days.
- This is an e-tender up to ₹2 crore → In consultation with associated finance, the period can be reduced to 14 days (opening on January 16); then validity = 3 × 14 = 42 days. However, due to having a notice period of less than 21 days, even if this tender were up to ₹50 lakh, it would not be dealt with through direct acceptance, but through a tender committee.
Summary Table
| Situation | Minimum Notice Period | Whose Consent |
|---|---|---|
| General Rule — Large works | Not less than 21 days | — |
| Extraordinary circumstances — Reducing below 21 days | Less than prescribed | Consultation with Principal Financial Adviser (PFA) |
| E-tenders up to ₹2 crore (inclusive) | Can be reduced up to 14 days | Consultation with Associated Finance |
| Remote location / Special nature / Works exceeding ₹50 crore | Sufficient — Not less than 21 days | — |
| Special Limited Tender | Not less than 14 days | — |
- Calculation of period — From the date of publication/uploading of the tender on the IREPS (e-tender portal) (Board's letter dated 26.07.2018 / 24.10.2018). The mandatory requirement of newspaper advertisements for e-tenders has been done away with.
- Old structure (2017, for information) — Up to ₹1 crore: 21 days (without financial consent); ₹1–2 crore: 14 days (with financial consent). In the old system, the normal period was one month.
- Direct acceptance (up to ₹50 lakh) is possible only when the notice period is 21 days or more — a tender with a shorter period will go to the Tender Committee.