10.1Core Principle — Negotiation is an Exception
In simple wordsPost-tender negotiation of rates with a contractor is not regular — only in exceptional cases, with reasons recorded in writing.
- Central Vigilance Commission (CVC) — Post-tender negotiation should generally not be held; it is a major source of corruption and delay.
- Negotiation only with L1 (lowest bidder) — and that too in extraordinary circumstances.
- Extraordinary circumstances (CVC) — Proprietary items, limited source items, and where cartelization is suspected.
- Negotiation should not be made a "regular process"; the Competent Authority should decide this on the recommendation of the TC (Tender Committee), with reasons.