5.1Three Components of Sanction
In simple wordsThree things are necessary for incurring expenditure on any work — Administrative Approval, Funds in the Budget (Allotment), and Technical Sanction (Detailed Estimate).
Why three separate ones? Answers to three different questions are required — (1) Is this work necessary? (Administrative Approval), (2) Is money available this year? (Budget/Funds), and (3) Are the design, quantities, and rates correct? (Technical Sanction). If even one of these three is absent, the expenditure will be considered irregular.
Example: Administrative approval for a yard remodeling (PH-16) was received in 2025-26, but no funds were allocated for it in the budget of 2026-27 → Contract cannot be awarded in this year, even if the detailed estimate is ready. Similarly, if funds are available but technical sanction of the detailed estimate has not been accorded → Inviting tenders is against the rules.
Summary Table
| Component | Meaning | Given By |
|---|---|---|
| Administrative Approval | Acceptance of the necessity of the work and the rough cost | Sanction of Abstract Estimate; Inclusion in the Budget (Pink Book) is generally considered as administrative approval of the Board |
| Expenditure Sanction / Funds | Provision in budget, allotment of funds | Budget, Grant, Re-appropriation |
| Technical Sanction | Correctness of design, quantities, and rates | Sanction of Detailed Estimate |