1.1What "Works Expenditure" Means
In simple wordsWorks expenditure = the Railways' spending on creating new assets or replacing/improving old ones — new lines, doubling, bridges, station buildings, etc. — and the rules governing it.
Difference between revenue and works expenditure — an example: Routine greasing, packing and minor repairs of the track are the cost of keeping the Railways running, so they are revenue expenditure (Working Expenses). But when the entire old track is removed and new rails and sleepers are laid (track renewal), that is a replacement of an asset — works expenditure, which will be recorded under Plan Head 31 and financed mainly from the DRF/RRSK.
- Railway expenditure is broadly of two kinds — revenue expenditure (Working Expenses) and works / capital-nature expenditure (Works Expenditure).
- Works expenditure = Assets — Acquisition, Construction and Replacement — new lines, doubling, gauge conversion, yards, bridges, buildings, signalling, electrification, Track Renewal, rolling stock, machinery, etc.
- This expenditure is recorded under Plan Heads and is financed from sources such as Capital, the Capital Fund, DRF (Depreciation Reserve Fund), DF (Development Fund), RSF (Railway Safety Fund), RRSK (Rashtriya Rail Sanraksha Kosh), EBR (deciding the source = allocation).
- Capital account Major Heads 5002 (commercial lines) and 5003 (strategic lines) — whatever the source of finance.
1.2Main Sources of Rules (Codes, Manuals, Orders)
In simple wordsThe main rule books — the Engineering Code (E), the Finance Code, the IRPWM (Indian Railways Permanent Way Manual), and the Board's orders/SOP.
Summary table
| Source | Subjects relating to works |
|---|---|
| Indian Railways Code for the Engineering Department (Engineering Code — "E") — revised edition 1982, fourth reprint 2012, with Advance Correction Slips (ACS) | Surveys, investment planning and works budget, Estimates, land, execution of works, contracts, initial records (MB — Measurement Book), works accounts, Completion Report, Deposit Works |
| Indian Railways Finance Code Vol. I (F-I) — second revised edition 2022 | Chapter II — Financial Appraisal of projects; Chapter III — budget; Chapter V — budgetary and expenditure control (register of works, monthly review); Chapter VII — allocation of expenditure |
| Finance Code Vol. II | Classification of expenditure and revenue (Appendix II — capital and other works expenditure) |
| Accounts Code (A-Code) | Accounting procedure, transfers, Suspense, Block Account |
| Model Schedule of Powers (Model SOP / MSOP) 2018 — Part A: Works | Powers of officers below the GM (re-delegation) |
| IRPSM (Indian Railways Projects Sanction & Management) portal | Work proposals, Works Programme, Umbrella distribution, sanction |
| IRUSSOR-2021 (issued by the Railway Board on 28.07.2022) | Unified standard schedule of rates for formation, bridge and P-way works; zonal USSORs are built from it |
| GCC (General Conditions of Contract) | Contract conditions (in detail in Module 11) |
Works rules come from several sources. The Engineering Code (revised 1982, reprinted 2012, with advance correction slips) is the main one, covering surveys, works budget, estimates, land, execution, contracts, measurement books, works accounts and completion reports. Finance Code Volume I (2022 edition) adds financial appraisal, the budget, expenditure control through the register of works, and allocation.
Finance Code Volume II classifies expenditure, the Accounts Code gives accounting procedure, and the Model Schedule of Powers 2018 (Part A) lays down officers' powers for works. The IRPSM portal handles work proposals, the works programme and sanctions, IRUSSOR-2021 gives unified standard rates for formation, bridge and track work, and the GCC sets contract conditions.
Abbreviation of code paras — e.g. "1101-E" = para 1 of Chapter XI of the Engineering Code; "521-F-I" = para 521 of Finance Code Vol. I.
1.3Engineering Code — Chapter-wise Map (for the exam)
In simple wordsA map of the chapters of the Engineering Code — which subject is in which chapter.
Summary table
| Chapter | Subject | Important paras |
|---|---|---|
| I | Organisation and administration | 101 — Open Line organisation (maintenance/renewal) vs Construction organisation |
| II | Methods of investigating railway projects | 201 project development process, 202 Viability study, 203 techno-economic survey, 204 classification of surveys |
| III | Traffic Survey | 301 definition, 302 objectives |
| IV | Engineering surveys — reconnaissance, preliminary, final location (FLS — Final Location Survey) | — |
| V | Project report, techno-economic survey report, viability report | 575 Financial Appraisal, 576 viability report |
| VI | Investment planning and works budget | Works Programme |
| VII | Estimates | 701 types, 702 abstract, 704 detailed, 707 supplementary, 708 revised, 709 Project Abstract, 710 construction, 713 completion, 727 Contingent Expenditure, 756 validity of sanction |
| VIII–IX | Rules and procedure for Land Acquisition | — |
| XI | Execution of works | 1101 commencement of work, 1103 urgency certificate, 1109–1113 Material Modification, 1123 order book, 1136 expenditure in excess of estimate, 1137–1138 Departmental Charges and exemptions |
| XII | Contracts | — |
| XIII | Initial records | Muster roll, measurement book (1313–1326), contractor's bills (1335–1341) |
| XIV | Accounts of works | 1436 materials at site, 1472 Register of Works, 1478 Expenditure Control, 1483 contractor's Ledger |
| XVII | Completion Report, Asset Register | 1704–1705, 1720 |
| XVIII | Miscellaneous works | Defence works, sidings (1827–1842), deposit works (1843–1854), quarries |
The Engineering Code is organised by chapter, and certain paras are asked often. Chapter I deals with organisation, distinguishing open line from construction (para 101). Chapters II–V cover investigation of projects, traffic and engineering surveys, and project reports, including financial appraisal (575) and the viability report (576). Chapter VI covers investment planning and the works programme.
Chapter VII covers estimates — types (701), abstract (702), detailed (704), supplementary (707), revised (708), project abstract (709), construction (710) and completion (713) estimates, contingencies (727) and validity (756). Chapters VIII–IX deal with land acquisition, XI with execution of works, including urgency certificates and material modification, XII with contracts, XIII with initial records such as the MB, XIV with works accounts and the register of works, XVII with completion reports, and XVIII with sidings and deposit works.
1.4Organisation — Who Does What
In simple wordsWho does what in a work — the executive (engineers), Associated Finance, accounts, and the sanctioning authorities.
Summary table
| Unit | Role |
|---|---|
| Railway Board — Gati Shakti Directorate (set up in May 2022) | Appraisal and sanction of projects, DPR/surveys, detailed/Revised Estimates and Material Modifications, EBR (Extended Board for Railways) meetings, Cabinet notes for the CCEA (Cabinet Committee on Economic Affairs) |
| Plan Head Coordinators — the Board's nodal directorates | Fixing zone-wise ceilings for Umbrella works |
| General Manager (GM) | Highest sanctioning power in the zone; re-delegation below through the MSOP |
| CE/P&D (Chief Engineer — Planning & Design) | Nodal officer in the zone for the Works Programme and Out-of-Turn works |
| DRM (Divisional Railway Manager) | Sanction of Lump sum works at divisional level |
| CAO/C (Chief Administrative Officer — Construction) | Execution of large projects |
| Gati Shakti Units (GSU) | Execution of projects at divisional level |
| Associate Finance — PFA (Principal Financial Adviser), FA&CAO(C), Sr.DFM | Vetting of estimates, Finance Concurrence, Tender Committee, checking of bills, Register of Works |
| External agencies — RVNL (Rail Vikas Nigam Limited), IRCON, RITES (Rail India Technical and Economic Service), DFCCIL (Dedicated Freight Corridor Corporation of India Limited), etc. | Execution of projects (on behalf of the Ministry of Railways) |
1.5Life Cycle of a Work
In simple wordsThe life cycle of every work — survey → sanction → estimate → Tender → execution → bills → completion.
- Identifying the need — at division/zone/Board level; for large projects, a survey / DPR (Detailed Project Report).
- Appraisal — financial (RoR/IRR) and technical; above ₹500 crore, the NPG (PM Gati Shakti), EBR/PIB.
- Administrative Approval — sanction of the Abstract Estimate; inclusion in the budget (Pink Book) is normally treated as the Board's administrative approval.
- Works Programme and budget — proposal on IRPSM (Indian Railways Projects Sanctions and Management) → Pink Book / LAW Book; or item-wise sanction by the GM/DRM under an Umbrella.
- Technical Sanction — sanction of the Detailed Estimate.
- Allotment of funds and tender → Contract Agreement.
- Execution — measurement book (MB), On-account Bills, materials, variations, and a Revised Estimate / Material Modification where needed.
- Accounting — Register of Works, contractor's Ledger, monthly review.
- Completion — Final Bill, Completion Report, Asset Register, asset in the block account.
Example — the journey of a foot over bridge (FOB):
- The division notices that passengers are crossing the tracks at a station → need for a new FOB.
- FOB = a passenger amenity → Plan Head 53; it is a small work, so a proposal (on IRPSM) for item-wise sanction by the GM/DRM within the zone's Umbrella ceiling.
- An abstract estimate (rough cost) is prepared → vetting by Associated Finance → administrative sanction by the Competent Authority.
- After drawings and design, a detailed estimate → technical sanction.
- Funds available → tender → contract.
- During the work, every measurement goes into the MB → on-account bills to the contractor; expenditure in the register of works.
- FOB complete → final bill → completion report → FOB entered in the asset register.
Every stage of this journey is covered in detail in the following sub-topics (2 to 21).
Exam trap
- "An order to prepare an estimate is not an authority to carry out the work" (1101-E) — to start a work you need a Sanctioned Estimate, budget provision/funds and (where required) vetting by Finance.
- Capital Major Heads 5002/5003 — the source (Capital/DRF/DF, etc.) is identified by a separate allocation code, not by a separate major head.
- IRUSSOR-2021 — for formation, bridge and P-way works; zones issue their own USSORs on this basis.
- Gati Shakti Directorate — created in 2022; the main directorate concerned with sanction of projects.
- Engineering Code Chapter VII = estimates, XI = execution, XIII = MB, XIV = works accounts, XVII = completion report, XVIII = deposit works/sidings.
1.6Gati Shakti Units (GSU) — structure, and the Project Monitoring Group (PMG)
Gati Shakti Units (Railway Board letter 27.07.2022)
- Decision to set up a GSU in all 68 divisions — a single unit in the division from the planning to the execution of projects.
- Head — the Chief Project Manager (CPM), under the administrative control of the DRM; the CPM post is open to all cadres except IRPFS (in a division with more than two ADRMs, one ADRM post is re-designated as CPM).
- The GSU has officers of civil, S&T, electrical, traffic and finance; associate finance — the division's Sr.DFM; a separate DFM/ADFM and SSO(A) for the GSU — functional control of the Sr.DFM, administrative control of the CPM.
- The establishment cost of the GSU is charged to the projects concerned.
- RET/PET surveys are now called "Feasibility Studies"; feasibility studies and DPRs are prepared only by the GSU.
- Sequence — the feasibility study is examined by the division's NPG (Network Planning Group) → approved by the DRM → permission to prepare the DPR from the GM → the DPR approved by the GM, with the concurrence of divisional finance (headquarters finance concurrence not required), goes directly to the Gati Shakti Directorate of the Railway Board; the process runs on IRPSM.
- In execution, the DRM and CPM have powers like the CAO/C and SAG officers of the construction organisation; at the zone the GM nominates an HAG/SAG officer as the zonal coordinator of the GSUs.
- Start — GSUs first in 5 divisions (Khurda Road, Bilaspur, Delhi, Bengaluru, Agra) (Board letters 16.05.2022 and 09.06.2022), then from 27.07.2022 in all remaining divisions.
- CPM/GS — under the administrative control of the DRM; the post is open to all cadres (except IRPFS), selection on the basis of ability and experience; in a division with more than two ADRMs, one ADRM post has been named CPM/GS.
- For large works (station redevelopment, major yard remodelling, coal/port connectivity, traffic facilities, ROB/RUB) there are SG/JAG/SS/JS officers of engineering, S&T, electrical and finance; the existing branches of the division continue to do the works of track renewals (PH-31), bridges (PH-32), staff welfare (PH-51) etc. as before.
- Expenditure on feasibility studies is charged to Demand No. 2, at the Board's rates, with finance concurrence.
- Supervision — PSSA/PMC may be engaged; with the DRM's approval, retired railway supervisors below 65 years of age may be engaged on contract, within the provision in the project estimate.
- GSU officers/senior supervisors — air travel outside the zone for Gati Shakti work, with the DRM's permission, without finance concurrence.
Project Monitoring Group (PMG)
- The institutional mechanism to remove bottlenecks in large projects (₹500 crore and above) — first in the Cabinet Secretariat (2013), placed under the Prime Minister's Office (PMO) in 2015, and merged into Invest India (DPIIT, Ministry of Commerce and Industry) in February 2019.
- Portal- and milestone-based monitoring; delays are identified and resolved with the ministries/states. (DPIIT was earlier called DIPP.)
Exam trapThe head of a GSU is the CPM (under the DRM); associate finance is the Sr.DFM; the feasibility study is approved by the DRM, and permission to prepare the DPR is given by the GM. The PMG is now in Invest India.