5.1Bottom-up Preparation
In simple wordsThe budget is not imposed from the top — units like divisions/workshops make their estimates, then the zone adds them up, then the Board examines them, then after discussion with the Ministry of Finance it goes to Parliament.
The railway budget is built from the grassroots level. As per the railway Finance Code, estimates start from units such as divisions, workshops, stores depots, because that is where the actual work and expenditure take place.
Sequence:
- Unit level (division/workshop/depot/construction organisation) — department-wise estimates; Accounts Officers (Sr. DFM etc.) scrutinise them.
- Zonal headquarters — estimates of PHODs (Principal Heads of Departments); the PFA/FA&CAO compiles and scrutinises; sent to the Railway Board with the GM's approval.
- Railway Board — scrutiny of estimates of all zones/PUs; RE (Revised Estimate) and BE (Budget Estimate) of each railway fixed; discussion of the Works Programme with the GM (General Manager).
- Ministry of Finance — discussion with the Board; GBS (Gross Budgetary Support) and total capital outlay fixed.
- Parliament — presented with the General Budget on 1 February.
Remember (sequence)Unit → zone (PFA, GM) → Railway Board → Ministry of Finance → Parliament.