Basic sourcesIndian Railways Signal Engineering Manual (IRSEM); G&SR (rules on signals and interlocking); RDSO's interlocking standards and specifications. The operating point of view — T.6.
1Interlocking — Basic Principles
In simple wordsInterlocking = such a mutual locking of signals, points and track that a wrong/unsafe signal simply cannot be given.
Interlocking = a relationship between signals, points and track detection such that a conflicting or unsafe situation cannot arise at all. Basic rules:
- A signal can be taken "off" only when all the points on the route are set in the correct position and locked, the route and overlap are clear (track circuits/axle counters), and conflicting signals are "on" and locked.
- While a signal is "off", the points on its route cannot move; the signals of a conflicting route cannot be taken "off".
- Fail-safe: any failure (broken wire, power failure, faulty relay) must take the signal to the "on" (most restrictive) position — never a wrong "off".
| Locking | Meaning |
|---|---|
| Approach locking | If a train has already approached the signal, the route is not released immediately even if the signal is put back to "on" — only after a prescribed time or after the train stops |
| Route holding / back locking | After the train passes the signal, the signal goes "on", but the route stays locked until the train has cleared the points/route |
| Sectional route release | As the train moves ahead, the sections behind it are released one by one — quick reuse of the yard |
| Side protection / isolation | A vehicle from an adjacent line must not run into the route — trap/isolation points |
2SIP and Control Tables
In simple wordsSIP = the signal-interlocking map of a yard; control table = the conditions on which each signal will clear.
- SIP (Signal Interlocking Plan): a diagram of the yard — all signals, points, track circuits/axle counters, overlaps, level crossings; based on the ESP (Engineering Scale Plan); jointly approved by operating, engineering and S&T.
- Control table: for every signal — which points in which position, which tracks clear, which signals "on", the overlap, the approach locking time, the conditions for route release. Interlocking is designed and tested from it.
- Standards of interlocking: Std I(R), II(R), III(R), IV(R) — more features as the permissible speed increases (e.g. completeness of track detection, point locking, number of signals).
3Signals
In simple wordsTypes of signals — colour-light (two-aspect, multiple-aspect), etc. and their aspects.
- Colour-light signals: two-aspect (red/green or red/yellow) and multiple-aspect (MACLS — red, yellow, double yellow, green); now LED signals — less power, longer life, better visibility; "lamp proving" (detecting a fused bulb/LED; if the red is fused, the signal in rear is restricted).
- Types: stop (home, starter, advanced starter, gate), permissive (distant), calling-on, shunt, route indicators (junction/loop), automatic signals ("A" marker).
- Signal sighting: the Loco Pilot must see it from an adequate distance — trees, OHE masts and structures must not obstruct it; joint inspection; sighting boards for fog.
4Kinds of Locking in Interlocking — Understood Through One Example
ExampleA train is to be taken from the main line to the loop line at a station — the home signal is to be taken "off", and point No. 12 in between must be "reverse".
Locking What happens in this example Point locking As soon as the signal is off, point 12 is locked in its (reverse) position — the point cannot move under the train Route locking All points, cross-overs and conflicting signals of the route are locked — no conflicting route can be set Approach locking If the train has approached the signal and the signal is put back to "on", the route is not released at once — only after the prescribed time (protection against a sudden change) Back locking/sectional route release As the train passes, the rear portions of the route are released one by one — for quick use by the next train Detection No signal "off" without confirmation that the point is actually set close in the correct position Track locking If a vehicle is standing on the route (track circuit/axle counter "occupied"), the signal does not come off
5Multiple Aspect Signals — the Sequence
| System | Aspects (from the front backwards, when the signal ahead is red) |
|---|---|
| 3-aspect | Red → yellow → green |
| 4-aspect | Red → yellow → double yellow → green |
ExampleIn a 4-aspect area the signal ahead is red → the one behind it shows yellow (next signal red, be prepared to stop), the one behind that double yellow (next signal yellow — start reducing speed), and the one behind that green. With 4 aspects, fast trains get a braking distance of two signal sections — hence its use on high-speed, short-headway sections.
6If Interlocking Fails — Non-interlocked Working (Principles)
- Report the failure and enter it in the register; call the S&T staff;
- all points on the route set by hand, clamped and padlocked; personal check;
- if the signal cannot be taken off, the train is passed on a written authority (prescribed form) or the calling-on signal, at restricted speed;
- after repair, testing and "fit" — then normal working.
NoteThat is why reducing failures matters for both safety and punctuality — failures are analysed with data loggers.
RememberQuick revision —
- Interlocking: points set and locked + route clear + conflicting signals on → only then signal off; fail-safe.
- Approach locking, route holding, sectional route release, side protection.
- SIP (based on the ESP) and control tables — the basis of design and testing.
- LED signals, MACLS, lamp proving; signal sighting.
Exam trap
- A signal comes off only when — points set and locked, route clear, conflicting signals on.
- Interlocking is fail-safe — the safe (red) state on failure.
- The SIP is based on the ESP.