रेल डिपार्टमेंटल तैयारीRail Departmental Taiyari — रेलवे विभागीय परीक्षाओं की तैयारीLogin / Open app

Principles of Interlocking, SIP, Control Tables and Signals

Signal & Telecommunication Engineering • Part 1 / 8 • ASTE (सिग्नल व दूरसंचार) full part free

हिंदी में पढ़ें

In this part

  1. Interlocking — Basic Principles
  2. SIP and Control Tables
  3. Signals
  4. Kinds of Locking in Interlocking — Understood Through One Example
  5. Multiple Aspect Signals — the Sequence
  6. If Interlocking Fails — Non-interlocked Working (Principles)
Basic sources

Indian Railways Signal Engineering Manual (IRSEM); G&SR (rules on signals and interlocking); RDSO's interlocking standards and specifications. The operating point of view — T.6.

1Interlocking — Basic Principles

In simple words

Interlocking = such a mutual locking of signals, points and track that a wrong/unsafe signal simply cannot be given.

Interlocking = a relationship between signals, points and track detection such that a conflicting or unsafe situation cannot arise at all. Basic rules:

Locking Meaning
Approach locking If a train has already approached the signal, the route is not released immediately even if the signal is put back to "on" — only after a prescribed time or after the train stops
Route holding / back locking After the train passes the signal, the signal goes "on", but the route stays locked until the train has cleared the points/route
Sectional route release As the train moves ahead, the sections behind it are released one by one — quick reuse of the yard
Side protection / isolation A vehicle from an adjacent line must not run into the route — trap/isolation points

2SIP and Control Tables

In simple words

SIP = the signal-interlocking map of a yard; control table = the conditions on which each signal will clear.

3Signals

In simple words

Types of signals — colour-light (two-aspect, multiple-aspect), etc. and their aspects.

4Kinds of Locking in Interlocking — Understood Through One Example

Example

A train is to be taken from the main line to the loop line at a station — the home signal is to be taken "off", and point No. 12 in between must be "reverse".

Locking What happens in this example
Point locking As soon as the signal is off, point 12 is locked in its (reverse) position — the point cannot move under the train
Route locking All points, cross-overs and conflicting signals of the route are locked — no conflicting route can be set
Approach locking If the train has approached the signal and the signal is put back to "on", the route is not released at once — only after the prescribed time (protection against a sudden change)
Back locking/sectional route release As the train passes, the rear portions of the route are released one by one — for quick use by the next train
Detection No signal "off" without confirmation that the point is actually set close in the correct position
Track locking If a vehicle is standing on the route (track circuit/axle counter "occupied"), the signal does not come off

5Multiple Aspect Signals — the Sequence

System Aspects (from the front backwards, when the signal ahead is red)
3-aspect Red → yellow → green
4-aspect Red → yellow → double yellow → green
Example

In a 4-aspect area the signal ahead is red → the one behind it shows yellow (next signal red, be prepared to stop), the one behind that double yellow (next signal yellow — start reducing speed), and the one behind that green. With 4 aspects, fast trains get a braking distance of two signal sections — hence its use on high-speed, short-headway sections.

6If Interlocking Fails — Non-interlocked Working (Principles)

Note

That is why reducing failures matters for both safety and punctuality — failures are analysed with data loggers.

Remember

Quick revision —

  • Interlocking: points set and locked + route clear + conflicting signals on → only then signal off; fail-safe.
  • Approach locking, route holding, sectional route release, side protection.
  • SIP (based on the ESP) and control tables — the basis of design and testing.
  • LED signals, MACLS, lamp proving; signal sighting.
Exam trap
  • A signal comes off only when — points set and locked, route clear, conflicting signals on.
  • Interlocking is fail-safe — the safe (red) state on failure.
  • The SIP is based on the ESP.
Full preparation in the app

All parts in Hindi + English, subject-wise MCQs and mock tests — create a free account.

Start free
All parts — Signal & Telecommunication Engineering
All exams & subjects (Hindi) • Login • शिक्षक भर्ती (RPSC / REET) नोट्स • Telegram channel • गोपनीयता नीति • नियम व शर्तें • संपर्क