1The most common confusions — with the correct answer
In simple wordsOn the left, the belief deliberately placed among options; on the right, the correct fact.
| Wrong belief | Correct fact |
|---|---|
| The head of stores in a division is the PCMM (Principal Chief Materials Manager) | In the zone PCMM; in the division Sr DMM |
| "Right department" is among the seven "rights" | Seven "rights" — material, quality, quantity, time, place, price, source |
| Splitting a requirement to fit powers is fine | Prohibited |
| Open tender above ₹25 lakh | ₹50 lakh and above (GFR 161, amendment 10.07.2024); limited up to ₹50 lakh |
| Value limit of special limited tender ₹50 lakh | Safety items — any value |
| Single tender any time "for shortage of time" | Only PAC (Proprietary Article Certificate), standardisation, emergency — reasons in writing |
| e-RA above ₹1 crore / still mandatory today | Stores — preferred for ₹10 crore+ in 2018, ₹5 crore+ from 08.08.2019; from 21.11.2024 not preferred, only one option; no negotiation after e-RA |
| GeM (Government e-Marketplace) is optional | Mandatory for available common goods/services (GFR 149) |
| Make in India Class-II — more than 50% | Class-I ≥50%; Class-II >20% and <50% |
| No global tender up to ₹500 crore | Normally none up to ₹200 crore |
| 4% + 3% in addition to MSE (Micro and Small Enterprises) 25% | The 4% and 3% are within the 25% |
| Land-border country restrictions since 2022 | Registration mandatory from 23.07.2020 |
| Both bids opened together in a two-bid system | Technical first; financial of qualified only |
| Negotiation with all bidders | Only with L1, in exceptional cases, reasons recorded |
| EMD (Earnest Money Deposit) 5–10% | EMD 2–5% (GFR 170); PG (Performance Guarantee) — GFR (General Financial Rules) 171: 3–10%, goods/services 3–5% (from 29.12.2023; earlier 5–10%) |
| Loss must be proved for LD (Liquidated Damages) | No — LD is pre-fixed; proof needed for GD |
| LD 2% per week | ½% per week or part of a week, maximum 10% (old rate 2% per month) |
| PVC (Price Variation Clause) in full even in the extended period | Up to the original delivery period; no benefit of price rises for the supplier's delay |
| Arbitration mandatory in every contract | 03.06.2024 — not automatic; normally below ₹10 crore |
| Government contracts in the officer's name | In the name of the President (Article 299) |
| Under CIF (Cost, Insurance and Freight), risk passes at destination | On loading — in all three of FOB/CFR/CIF |
| CIF insurance 100% | 110% |
| EXW (Ex Works) has the seller's maximum obligation | EXW minimum; DDP (Delivered Duty Paid) maximum |
| Under an LC (Letter of Credit) the bank pays after seeing the goods | After seeing the documents (UCP 600) |
| R-Note for the quantity dispatched | For the accepted quantity |
| The Railway returns rejected goods | The supplier removes them at his own cost |
| FIFO (First In, First Out) equally for all items | Especially for limited-life items |
| PL (Price List) number of 6 digits, different for each zone | 8 digits, one across IR |
| Dues-in are not deducted in provisioning | They are deducted — (stock + dues-in) |
| In EOQ (Economic Order Quantity), C = total carrying cost | Annual carrying cost per unit |
| XYZ — on usage value | XYZ — value lying in stock; ABC — usage value |
| Higher Railway turnover ratio = good | Lower = good |
| ±10% is allowed in scrap delivery | Not more than the lot — weighment and witness |