1What a Primary Unit is
In simple wordsThe last two digits of every expenditure code tell on what the money was spent — salary, stores material, fuel or a contractor. These two digits are called the Primary Unit (PU) or object of expenditure.
- Order of classification — Major Head → Sub-Major Head → Minor Head → Sub Head → Detailed Head → Primary Unit (object head).
- The heads say "which activity" (for example repair of engines); the PU says "on which element" (wages/material/other).
- PUs allow expenditure to be analysed by element of cost — so a classification is "complete" only when the PU is also given.
Main Primary Units of revenue expenditure
| PU | On what |
|---|---|
| 01 | Salaries and wages |
| 02 | Dearness allowance |
| 03 | Productivity Linked Bonus (PLB) |
| 24 | Printing and stationery |
| 27 | Cost of material drawn from stock |
| 28 | Cost of material — direct purchase |
| 31 | Fuel other than for traction — track machines, generator sets, road vehicles; bio-diesel (other than traction) — direct purchase or from stock |
| 32 | Contractual payments — works and handling contracts, contracts for engineering supply of material (all other direct purchases go to PU 28) |
| 33 | Transfer of debits/credits from one unit to another — e.g. POH (Periodical Overhaul) debits to revenue heads of a foreign (other) railway; locomotive GTKM (Gross Tonne Kilometre) debits/credits go to PU 61 from 2015 |
| 34 / 35 | Adjustment of wages / material for POH and repairs from WMS (Workshop Manufacture Suspense) to revenue heads of the home railway |
| 49 | Expenditure on outsourcing of manpower/activities for track maintenance |
Primary Units classify revenue expenditure by its nature, regardless of which department spends it. PU 01 is salaries and wages, 02 dearness allowance and 03 Productivity Linked Bonus. PU 24 is printing and stationery.
PU 27 is the cost of material drawn from stock, and PU 28 material bought directly. PU 31 is fuel used for purposes other than traction, such as track machines, generator sets and road vehicles. PU 32 is contractual payments for works, handling and engineering supply. PU 33 records transfers of debits and credits between units, such as POH debits to another railway. PU 34/35 adjust wages and material for POH and repairs from WMS to the home railway's revenue heads. For example, a contractor's bill for track maintenance goes to PU 32, while rails issued from the depot go to PU 27.
Primary Units for works (capital etc.)
| PU | On what |
|---|---|
| 01 | Pay and allowances of departmental establishment |
| 02 | Casual labour |
| 03 | Payments to contractors (works/supply-and-erection contracts) |
| 04 | Direct supply of material |
| 05 | Stores supplied from stock (depot) |
| 06 | Freight on stores |
| 07 | Credits for released material |
| 08 | Others |
Works expenditure has its own set of Primary Units. PU 01 is pay and allowances of departmental establishment and PU 02 casual labour. PU 03 is payments to contractors under works or supply-and-erection contracts.
PU 04 is material supplied directly and PU 05 stores supplied from the depot. PU 06 is freight on stores, PU 07 records credits for material released from the work, and PU 08 covers everything else. The split lets the cost of a work be analysed into labour, contract, material and freight, which is useful for comparing actual cost with the estimate.
ExampleRails worth ₹5 lakh are drawn from the depot for a plan-head work — in capital this is PU 05 (stores from stock). Old rails released from the same work are credited to the depot at ₹1.2 lakh — PU 07 (credit for released material). Diesel issued from stock for a track machine under revenue — PU 31.
Exam trapRevenue PU 05 and works PU 05 are different things — if the question says "material from depot for a capital work", the answer is PU 05; if it says "material from stock under revenue", it is PU 27.