1Production documents
In simple wordsEvery job in a workshop runs on paper (now digital) — which operations in what order (process sheet), how much time which artisan took (job card), what material was drawn (requisition), and which route the part took (route card). Costs and incentives are built from these.
| Document | Use |
|---|---|
| Process sheet (M.608) | Sequence of operations; the Rate Fixer adds the Preparatory Allowance (PA) and Allowed Time (AT) to it |
| Job card | Start and finish time of each operation; pink card for replacement work |
| Squad card / squad summary card | Labour hours of work done as a group |
| Proceeding Time Card | Carries the time of incomplete work at month-end into the next month |
| Material requisition (M.611 A/B), material tag | Drawal of material and its identification with the job |
| Route Card (M.612) | Like the process sheet, plus the inspection record; travels with the material until delivery to stores |
Production documents record what is done to each job and how long it took. The process sheet (M.608) lists the sequence of operations, and the Rate Fixer adds the preparatory allowance and allowed time to it — the basis of incentive. The job card records the start and finish of each operation, with a pink card for replacement work.
A squad card records hours when a group works together. A proceeding time card carries the time of work still incomplete at month-end into the next month, so that no time is lost or double-counted. The material requisition (M.611 A/B) and material tag record the drawal of material and identify it with the job. The route card (M.612) is like the process sheet but also records inspection, and it travels with the material until delivery to stores.
Remember"608 process, 611 requisition, 612 route" — and pink card = replacement.
Example (proceeding time card)Machining of an axle began on 29 March; 14 hours were spent by 31 March and the job was incomplete. These 14 hours are carried into April through a proceeding time card, so that on completion the total time (and incentive) works out correctly; March's labour is already booked to cost, but the job remains in work in progress (WIP).