Workshops, Production Units and the Workshop Accounts Organisation

Workshop Accounts • Part 1 / 14 • Appendix-III A IREM Examination full part free

हिंदी में पढ़ें

In this part

  1. What Workshops Are For
  2. Production Units
  3. Workshop Accounts Organisation
  4. Information System, Investment Planning and Capacity
  5. Which Account Head Workshop Expenditure Goes To
  6. Internal Check by the WAO — What Is Examined
  7. Indicators of Workshop Performance

1What Workshops Are For

In simple words

Just as a car gets a major servicing every few years, locomotives and coaches are completely opened up and repaired at fixed intervals — this is called Periodical Overhaul (POH). It is done in zonal workshops. New locomotives and coaches are built in Production Units (PU).

Zonal workshops

  1. Periodical Overhaul (POH) of rolling stock — locomotives, coaches, wagons;
  2. Intermediate and accident repairs, rebuilding, modernisation;
  3. Manufacture of components — which go to stores;
  4. Work for other railways and outside parties.

Head — Chief Workshop Manager (CWM).

Production Units (PU)

Organisation on a zone

Post Role
Principal Chief Mechanical Engineer (PCME) Directly responsible to the GM for the maintenance of rolling stock
Chief Workshop Engineer (CWE) Coordination of workshops
CWM Head of each workshop; shop in-charges under him
In detail

On a zonal railway, the mechanical department's workshops sit under a clear chain of command. The Principal Chief Mechanical Engineer (PCME) is directly responsible to the General Manager for the maintenance of all rolling stock, so overall responsibility for workshops rests with him.

The Chief Workshop Engineer (CWE) coordinates the work of the different workshops — their programmes, capacity and priorities. Each workshop is headed by a Chief Workshop Manager (CWM), under whom the individual shops are run by shop in-charges. For accounts purposes, the CWM is the executive with whom the Workshop Accounts Officer deals day to day.

Remember

Order on a zone — PCME → CWE → CWM → shop; whereas a Production Unit is directly Board → GM (PU).

Rolling stock policy: specifications and design on the basis of "Life Cycle Cost" (Board and RDSO). Manufacture — Production Units, zonal workshops, outside manufacturers.

2Production Units

Unit Location Main products
CLW Chittaranjan (West Bengal) Electric locomotives
BLW (formerly DLW) Varanasi Electric locomotives (WAG-9, WAP-7), Amrit Bharat locomotives, diesel locomotives for export
PLW (formerly DMW) Patiala Electric locomotives, components
ICF (Integral Coach Factory) Chennai Coaches, Vande Bharat, EMU/MEMU
RCF (Rail Coach Factory) Kapurthala LHB (Linke Hofmann Busch) coaches
MCF (Modern Coach Factory) Rae Bareli LHB coaches
RWF (Rail Wheel Factory) Bengaluru (Yelahanka) Wheels and axles
RWP (Rail Wheel Plant) Bela (Bihar) Wheels
In detail

Production units manufacture new rolling stock and components, unlike zonal workshops, which repair and overhaul. CLW, Chittaranjan in West Bengal makes electric locomotives. BLW, Varanasi (formerly DLW) makes electric locomotives such as the WAG-9 and WAP-7, Amrit Bharat locomotives, and diesel locomotives for export. PLW, Patiala (formerly DMW) makes electric locomotives and components.

On the coach side, ICF, Chennai makes coaches including Vande Bharat trains and EMU/MEMU stock, while RCF, Kapurthala and MCF, Rae Bareli make LHB coaches. RWF, Bengaluru (Yelahanka) makes wheels and axles, and RWP, Bela in Bihar makes wheels. A common exam trap is the renaming: DLW became BLW and DMW became PLW, both now making electric locomotives.

Besides these, there are joint venture (JV) locomotive factories — Madhepura (electric locomotives) and Marhaura (diesel locomotives).

Remember

Locomotives — C-B-P (CLW, BLW, PLW); coaches — I-R-M (ICF, RCF, MCF); wheels — RWF, RWP.

Production in 2025-26

Item Number
Total locomotives 1,674
Total LHB coaches 6,677
BLW (Banaras Locomotive Works) locomotives (highest ever) 572
ICF coaches (highest ever) 3,405
MCF coaches (highest ever) 2,126

3Workshop Accounts Organisation

In simple words

Every large workshop has an accounts office within it — the Workshop Accounts Officer (WAO) — who works under the PFA and keeps account of the workshop's expenditure and costs.

WAO / Deputy Chief Accounts Officer (Workshop) — under the PFA, located in the workshop itself.

Functions of accounts

  1. Costing — work orders, cost sheets, unit costs;
  2. Time-keeping and labour accounts; check of incentive payments;
  3. Accounting of materials — issues, returns, workshop stores;
  4. Workshop Manufacture Suspense (WMS) — outturn statements, adjustments;
  5. Revision of estimates; recovery for outside work;
  6. Budget and review of on-cost;
  7. Cost reports for management.
Definition — total cost of ownership

the total expenditure on a locomotive/coach over its whole life — purchase + all POHs + repairs. The ultimate aim of cost accounting is to know this, so that the decision "continue repairing or replace" can be taken (ERP-based).

4Information System, Investment Planning and Capacity

Subject Key points
WISE (Chapter 8) Workshop Information System — arrival of rolling stock for POH, maintenance job orders, lists of work, despatch date and next POH date online; linkage with the stores system is required for materials
Investment planning (Chapter 10) Plan Head 21 — Rolling Stock; 41 — Machinery and Plant (M&P); 42 — Workshops and Production Units; Rolling Stock Programme (RSP) and M&P programme with the budget; condemnation and replacement on completing codal life
Capacity optimisation (Chapter 11) Full use of available capacity; work for outside parties only when there is surplus capacity (sub-topic 8)
Obligations towards staff (Chapters 3–4) Workshops are now within the scope of the OSH (Occupational Safety and Health) Code 2020 — rules on safety, working hours and welfare
In detail

Several chapters of the workshop code deal with systems and planning. WISE (Chapter 8) is the Workshop Information System: it records online the arrival of rolling stock for POH, job orders, lists of work, the despatch date and the next POH date, and is linked with the stores system. Investment planning (Chapter 10) uses three plan heads — 21 for rolling stock, 41 for machinery and plant, and 42 for workshops and production units — through the Rolling Stock Programme and the M&P programme prepared with the budget.

Capacity optimisation (Chapter 11) requires full use of the capacity available; work for outside parties is taken only when there is surplus capacity. Obligations towards staff (Chapters 3–4) now fall under the OSH Code 2020, which governs safety, working hours and welfare in workshops.

5Which Account Head Workshop Expenditure Goes To

In simple words

In a workshop, wages, materials and on-cost are first collected in an "in-between account" — the Workshop Manufacture Suspense (WMS). When the job is complete, the cost moves from there to the head for which the work was done — locomotive repairs, coach repairs, a new asset, or an outside party.

Work Final head
POH/repairs of locomotives (motive power) Revenue — SMH 03 (motive power — repairs and maintenance; Abstract C)
POH of coaches/wagons Revenue — SMH 04 (carriages and wagons — repairs and maintenance; Abstract D)
Repairs of plant/equipment Revenue — SMH 05 (Sub-Major Head)
Manufacture of components for stores Stores Suspense (stock in depot) — then the user on issue
New asset (capital work) Capital/DRF/DF — the work concerned
Work for an outside party Recovery from the party (adjusted against the advance deposit)
In detail

Workshop expenditure is first collected in Workshop Manufacture Suspense and then cleared to the head that represents what the work was for. POH and repairs of locomotives go to revenue SMH 03 (motive power — repairs and maintenance), and POH of coaches and wagons to SMH 04 (carriages and wagons — repairs and maintenance). Repairs of plant and equipment go to SMH 05.

Components made for stores go first to Stores Suspense as depot stock and are charged to the user when issued. A new asset is charged to Capital, DRF or DF, as the work concerned is financed. Work for an outside party is recovered from that party, adjusted against its advance deposit. The rule is simple: the final head follows the purpose of the work, not the shop in which it was done.

Example

In a month, a workshop spent ₹5 crore — wages ₹2 crore, materials ₹2.2 crore, on-cost ₹0.8 crore — all first to WMS. That month the POH of 30 coaches was completed (₹3.6 crore) → SMH 04; POH of 2 locomotives (₹0.9 crore) → SMH 03; components worth ₹0.3 crore to stores → Stores Suspense. The remaining ₹0.2 crore will stay in WMS as work-in-progress.

6Internal Check by the WAO — What Is Examined

Area Points of check
Time-keeping Matching attendance (gate) with time on jobs (job cards); analysis of idle time; sanction for overtime
Incentive Sanction of allowed time (AT), time taken (TT), limit of profit %, review of unusually high profits (sub-topic 6)
Materials Issue notes as per the work order; consumption above the standard; prescribed proportion of scrap; credit for returned material
Work orders Sanction, expenditure above the Estimate, timely closure, old open work orders
WMS Analysis of the balance, long-pending items, timely transfer to the final head
Outside work Advance deposit, proforma on-cost, recovery of actual cost
Machinery Utilisation of M&P, idle machines, cost of repairs
In detail

The Workshop Accounts Officer's internal check covers every area where workshop money can leak. In time-keeping, gate attendance is matched with time booked on job cards, idle time is analysed and overtime sanction is checked. In incentive, the allowed time, time taken and the profit limit are checked, and unusually high profits are reviewed.

For materials, issue notes must agree with the work order, consumption above standard is questioned, scrap must be returned in the prescribed proportion, and returned material must be credited. Work orders are checked for sanction, expenditure above the estimate, timely closure and long-open orders. The WMS balance is analysed for long-pending items. Outside work needs an advance deposit, proforma on-cost and recovery of actual cost, and machinery is examined for utilisation, idle machines and cost of repairs.

7Indicators of Workshop Performance

In simple words

Whether a workshop is doing well shows up in a few figures: how many units came out, how many days they took, what they cost, and how many man-hours were used.

Indicator Meaning Good when
Out-turn Units turned out after POH in a month/year Equal to or above target
Workshop days / cycle time How many days a unit stayed in the workshop Low
Unit repair cost (URC) POH cost per unit (sub-topic 2) Below/equal to the standard
Man-hours per unit Labour productivity Low
Ratio of on-cost to direct labour Burden of indirect expenses Low
In detail

A workshop's performance is judged by a handful of indicators. Out-turn — the number of units turned out after POH in a month or year — should equal or exceed the target. Workshop days or cycle time — how long a unit stays in the workshop — should be low, because every day in the shop is a day lost to traffic.

The Unit Repair Cost should be at or below the standard, and man-hours per unit should be low, showing good labour productivity. The ratio of on-cost to direct labour should be low, since a high ratio means indirect expenses are heavy relative to productive work. For example, a coach workshop that turns out its target of 100 coaches but takes 18 days each instead of 14 is meeting volume but keeping stock out of service too long.

Example

In a workshop, the POH of a coach took 24 days on average last year and 20 days this year → coaches returned to service sooner; this means more passenger service from the same number of coaches, i.e. fewer "ineffective" coaches.

Summary table

Point Key facts
Code Rolling Stock Code October 2022 (formerly the Mechanical Department (Workshops) Code)
Workshops POH, accident repairs, components, outside work; headed by the CWM
Zone PCME → CWE → CWM
PU Directly under the Board; headed by a GM; own PFA; batch costing
Locomotives / coaches / wheels CLW, BLW, PLW (Patiala Locomotive Works) / ICF, RCF, MCF / RWF, RWP; JV — Madhepura, Marhaura
2025-26 1,674 locomotives; 6,677 LHB coaches; BLW 572; ICF 3,405; MCF 2,126
Accounts WAO — under the PFA; costing, time-keeping, materials, WMS, incentive, Estimates, on-cost
Plan Heads 21 rolling stock, 41 M&P, 42 workshops/PUs
WISE Online management of POH; linkage with the stores system
Full preparation in the app

All parts in Hindi + English, subject-wise MCQs and mock tests — create a free account.

Start free
All parts — Workshop AccountsNext: Systems of Costing and Unit Repair Cost (URC) ›
All exams & subjects (Hindi) • Login • शिक्षक भर्ती (RPSC / REET) नोट्स • Telegram channel • गोपनीयता नीति • नियम व शर्तें • संपर्क