| A bill of another government department is paid in cash |
Settled by transfer/remittance |
| On partial disallowance the whole bill is held up |
The balance is paid |
| Contractor TDS (Tax Deducted at Source) — Section 194C (in 2026-27) |
From 01.04.2026 Section 393(1) (old 194C); salary 392 |
| Contractor TDS — company 1% |
Individual/HUF 1%, others 2%; 20% if no PAN (Permanent Account Number) |
| GST (Goods and Services Tax) TDS on the full bill amount |
2% on the taxable value; contract above ₹2.5 lakh |
| BOCW (Building and Other Construction Workers) cess 2% |
1% |
| SD (Security Deposit) — 5% of every bill |
6% of every bill, up to a total of 5% |
| Attachment — 1/3 of the whole salary |
Ordinary decree — first ₹1,000 + 2/3 of the rest exempt; up to 1/3 in maintenance |
| CTG (Composite Transfer Grant) even on a transfer on request |
No TA/CTG |
| CTG — 100% of Basic Pay |
80%; 1/3 of it within 20 km |
| HBA (House Building Advance) — 34 months or ₹25 lakh, whichever is more |
Whichever is least (cost and capacity too) |
| HBA recovery — 240 instalments of principal |
Principal 180, then interest 60 |
| NPS (National Pension System) — 10% + 10% |
10% + 14% (UPS 10% + 18.5%) |
| An SRPF (State Railway Provident Fund) Final Withdrawal has to be repaid |
A Temporary Advance is repaid; a Final Withdrawal is not |
| Abstract Estimate → Technical Sanction |
Abstract → administrative approval; detailed → technical |
| Revised Estimate for an omitted item |
Omitted item → supplementary; cost up ≈10%+ → revised |
| Validity of sanction 3 years |
5 years; 2 years if not started |
| Above ₹500 crore — CCEA (Cabinet Committee on Economic Affairs) |
Above ₹1,000 crore — CCEA; ₹500 crore+ — NPG (Network Planning Group) |
| Zonal contract 3 years |
Normally 1 year |
| Eligibility — 1 similar work of 35% is enough |
Technical — 3×30% / 2×40% / 1×60% (7 years); financial — V/N or V (lower) (ACS-1) |
| Bid Capacity above ₹20 crore |
From ACS-11, above ₹10 crore |
| EMD (Earnest Money Deposit) — 2% up to ₹1 crore, 0.5% beyond |
From ACS-11 (13.03.2026) 2% on all works |
| MSE (Micro and Small Enterprises) preference in works too |
Only in goods/services |
| APG (Additional Performance Guarantee) on every low bid |
+5% if more than 5% below the advertised value |
| PG — within 30 days of LOA (Letter of Acceptance) |
21 days (up to 60, 12% penal interest) |
| The successful bidder's EMD is converted into PG |
It is converted into SD |
| Sub-contracting up to 50% |
40% (unchanged in ACS-12 too) |
| 17B LD (Liquidated Damages) — 2% per month |
0.05–0.30% per week, maximum 5% |
| Bonus — for every 15 days |
1% for every full 30 days, maximum 5% |
| Variation — contract rate up to 140% |
Contract rate up to 125%; 98% up to 140%; 96% up to 150% |
| Reduced rate on the whole quantity |
Only on the extra portion |
| 25% limit on foundation items |
No limit |
| PVC (Price Variation Clause) — above ₹50 lakh |
Contract agreement value ₹2 crore+; not zonal/AMC; 15% fixed |
| PVC increase even during the contractor's delay |
No benefit; if prices fall, the Railway benefits |
| Mobilisation advance in every contract |
Only in large contracts where the tender provides; 10%; BG 110%; recovery 15% → 85% |
| Bonus (17C) in every contract |
Only open tender, ₹50 crore+, period 12 months+, scope not reduced by more than 10%, no extension of time |
| Secured advance on all material |
Imperishable material, up to 75% |
| Imprest — recouped after cutting the objected item |
Full recoupment; the objected item goes to "Miscellaneous Advances" |
| No report if the loss has been made good |
Report all the same |
| Deposit works — money after the work |
Cost + departmental charges deposited first |