रेल डिपार्टमेंटल तैयारीRail Departmental Taiyari — रेलवे विभागीय परीक्षाओं की तैयारीLogin / Open app

Demurrage, Wharfage, Sidings and Terminals

Traffic Accounts and Statistics • Part 4 / 24 • Appendix-III A IREM Examination

हिंदी में पढ़ें

In this part

  1. Demurrage and wharfage — the difference
  2. Check and waiver
  3. Cranes, sidings and terminals
  4. Current demurrage rates — graded structure
  5. Wharfage rates and goods-shed groups
  6. Waiver — from 1 July 2025
  7. A. New waiver/write-off guidelines — Corrigendum 60 (dated 23.02.2026)

First sub-topic (sample)

1Demurrage and wharfage — the difference

In simple words

Demurrage — the customer kept a wagon beyond the free time for loading/unloading, so the railway's wagon was held up — this is the charge for it. Wharfage — unloaded goods stayed on railway premises beyond the free time, so space was held up — this is the charge for it.

Point Demurrage Wharfage
On what Detaining wagons Keeping goods
Basis Per wagon per hour Now per wagon per hour — rate by goods-shed group (earlier per tonne)
Purpose Quick release of wagons Clearing goods-shed space
When After the free time for loading/unloading After the free time following unloading
In detail

Demurrage and wharfage are both charges for delay, but they are levied on different things. Demurrage is charged for detaining the Railway's wagons beyond the free time allowed for loading or unloading, at a rate per wagon per hour. Its purpose is to get wagons released quickly so they can earn again.

Wharfage is charged for leaving goods on railway premises after the free time that follows unloading. It used to be charged per tonne, but it is now also charged per wagon per hour, at a rate that depends on the goods-shed group. Its purpose is to keep the goods shed clear for the next rake. A simple way to remember: demurrage is about the wagon standing idle, wharfage is about the platform space being blocked.

Solved example (notional rates)

A rake of 40 wagons; free time for unloading (assume) 9 hours; rake released in 15 hours; rate (assume) ₹150 per wagon per hour.

Extra time = 15 − 9 = 6 hours → demurrage = 40 × 6 × 150 = ₹36,000.

The unloaded goods (of 40 wagons) stayed 10 more hours after the free time for removal; wharfage rate at a Group II goods shed ₹120 per wagon per hour → 40 × 10 × 120 = ₹48,000.

(Actual free time and rates are taken from commercial circulars.)

Full preparation in the app

All parts in Hindi + English, subject-wise MCQs and mock tests — create a free account.

Start free
‹ Previous: Check of Goods Earnings — Freight, Wrong Invoices and Through EarningsAll parts — Traffic Accounts and StatisticsNext: Station Accounts, Station Balance Sheet and Outside Booking Agencies ›
All exams & subjects (Hindi) • Login • शिक्षक भर्ती (RPSC / REET) नोट्स • Telegram channel • गोपनीयता नीति • नियम व शर्तें • संपर्क